| 1 | Providing Garbage Collection and Disposal Systems (100 nos. Equipment & Vehicles — PANIPAT(DC CUM NODAL OFFICER MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 604 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹42.81 L | HIGH 73
delay 25cost 20duplication 20 | |
| 2 | Providing Garbage Collection and Disposal Systems (100 nos. Equipment & Vehicles — PANIPAT(DC CUM NODAL OFFICER MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 604 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹17.90 L | MEDIUM 69
delay 25duplication 20cost 16 | |
| 3 | Providing Garbage Collection and Disposal Systems (100 nos. Equipment & Vehicles — PANIPAT(DC CUM NODAL OFFICER MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 604 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹15.14 L | MEDIUM 68
delay 25duplication 20cost 15 | |
| 4 | Providing Garbage Collection and Disposal Systems (100 nos. Equipment & Vehicles — PANIPAT(DC CUM NODAL OFFICER MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 604 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹14.54 L | MEDIUM 67
delay 25duplication 20cost 14 | |
| 5 | Providing Garbage Collection and Disposal Systems (100 nos. Equipment & Vehicles — PANIPAT(DC CUM NODAL OFFICER MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 604 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹7.44 L | MEDIUM 63
delay 25duplication 20cost 11 | |
| 6 | Providing Garbage Collection and Disposal Systems (100 nos. Equipment & Vehicles — PANIPAT(DC CUM NODAL OFFICER MPLADS) - 604 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹4.34 L | MEDIUM 61
delay 25duplication 20cost 8 | |
| 7 | Construction of Community Chaupalat Vilage Nanhera, Block Sa Community Buildings — PANIPAT(DC CUM NODAL OFFICER MPLADS) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in PANIPAT (100% above, 34 peer works)
- 632 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹10.00 L | MEDIUM 58 | |
| 8 | Const. of a big hall/room on panchayat land near shitla mata Community Buildings — PANIPAT(DC CUM NODAL OFFICER MPLADS) - ₹1,100,000 against a ₹500,000 median for Community Buildings works in PANIPAT (120% above, 34 peer works)
- 653 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹11.00 L | MEDIUM 58 | |
| 9 | CConst. of Shed on panchayat land near gaushala inVillage Ku Community Buildings — PANIPAT(DC CUM NODAL OFFICER MPLADS) - ₹1,400,000 against a ₹500,000 median for Community Buildings works in PANIPAT (180% above, 34 peer works)
- 653 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹14.00 L | MEDIUM 58 | |
| 10 | Construction of Dr. B. R. Ambedkar Bhawan at Village Goyla K Community Buildings — PANIPAT(DC CUM NODAL OFFICER MPLADS) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in PANIPAT (100% above, 34 peer works)
- 653 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹10.00 L | MEDIUM 58 | |
| 11 | Const. of a Hall/shed and rooms at padyan chaupal at village Community Buildings — PANIPAT(DC CUM NODAL OFFICER MPLADS) - ₹1,100,000 against a ₹500,000 median for Community Buildings works in PANIPAT (120% above, 34 peer works)
- 653 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹11.00 L | MEDIUM 58 | |
| 12 | installation of Tower Lights Street Lighting — PANIPAT(DC CUM NODAL OFFICER MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 211 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹48.71 L | MEDIUM 52 | |
| 13 | Construction of road from Phirni to Canel Roads & Paving — PANIPAT(DC CUM NODAL OFFICER MPLADS) - ₹1,500,000 against a ₹699,000 median for Roads & Paving works in PANIPAT (115% above, 16 peer works)
- 126 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹15.00 L | MEDIUM 50 | |
| 14 | Purchase fo Ultrasound Machine with Color Doppler MOddel ver Health — PANIPAT(DC CUM NODAL OFFICER MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 596 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹25.00 L | MEDIUM 50 | |
| 15 | Const. of retaining Wall of kund near Baba Sardus Maharaj Ma Religious & Cultural — PANIPAT(DC CUM NODAL OFFICER MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 658 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹11.00 L | MEDIUM 47 | |
| 16 | installation of 10kw solar system in Govt. model sanskriti s Education — PANIPAT(DC CUM NODAL OFFICER MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 612 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹10.00 L | MEDIUM 45 | |
| 17 | Construction of a Big Hal at Valmiki Chaupal at Village Nara Community Buildings — PANIPAT(DC CUM NODAL OFFICER MPLADS) - 665 days beyond expected completion
- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹5.00 L | MEDIUM 42 | |
| 18 | Construction of street from Babail Road and Sanoli Road to H Roads & Paving — PANIPAT(DC CUM NODAL OFFICER MPLADS) - 544 days beyond expected completion
- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹1.00 L | MEDIUM 42 | |
| 19 | construction of wall for CH. DEVI LAL Memorial girls (PG) Co Roads & Paving — PANIPAT(DC CUM NODAL OFFICER MPLADS) - ₹1,098,412 against a ₹699,000 median for Roads & Paving works in PANIPAT (57% above, 16 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹10.98 L | MEDIUM 42
duplication 20cost 14agency 8 | |
| 20 | construction of wall for CH. DEVI LAL Memorial girls (PG) Co Roads & Paving — PANIPAT(DC CUM NODAL OFFICER MPLADS) - ₹1,098,412 against a ₹699,000 median for Roads & Paving works in PANIPAT (57% above, 16 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹10.98 L | MEDIUM 42
duplication 20cost 14agency 8 | |
| 21 | Completion of Building and laying of floors at Primary Schoo Education — PANIPAT(DC CUM NODAL OFFICER MPLADS) - 664 days beyond expected completion
- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹5.00 L | MEDIUM 42 | |
| 22 | Construction of Ambedkar Bhawan, Near Valmiki Mandir in Vill Community Buildings — PANIPAT(DC CUM NODAL OFFICER MPLADS) - 653 days beyond expected completion
- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹5.00 L | MEDIUM 42 | |
| 23 | Completion of BC Chaupal ward No. 6, Balana, Israna Community Buildings — PANIPAT(DC CUM NODAL OFFICER MPLADS) - 653 days beyond expected completion
- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹5.00 L | MEDIUM 42 | |
| 24 | Construction of Jogi Chaupal at Village Sutana, Block Madlau Community Buildings — PANIPAT(DC CUM NODAL OFFICER MPLADS) - 653 days beyond expected completion
- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹5.00 L | MEDIUM 42 | |
| 25 | Completion of Valmiki Chaupal (Chhoti) in Village Seenk, Blo Community Buildings — PANIPAT(DC CUM NODAL OFFICER MPLADS) - 653 days beyond expected completion
- Implementing agency has a 52% delay rate across its projects
| PANIPAT | ₹5.00 L | MEDIUM 42 | |