Const. of a big hall/room on panchayat land near shitla mata
Community Buildings
Haryana / PANIPAT — PANIPAT(DC CUM NODAL OFFICER MPLADS) · Sanjay Bhatia (KARNAL)
Const. of a big hall/room on panchayat land near shitla mata mandir at Village Machhrauli
Overall risk score
58/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency52
Compliance0
Sanctioned
₹11.00 L
Delay
653d
Cost deviation
120%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹1,100,000 against a ₹500,000 median for Community Buildings works in PANIPAT (120% above, 34 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 653 days beyond expected completionPublished dates
- Implementing agency has a 52% delay rate across its projectsStated compliance rule
Decision trail
Nobody has recorded a decision on this work yet.