| 1 | Construction of Firni Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹6,996,000 against a ₹602,000 median for Roads & Paving works in PALWAL (1062% above, 78 peer works)
- 553 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹69.96 L | MEDIUM 59 | |
| 2 | Const. of hall Saheed Mahipal Park Asawta Selothi Road palwa Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹1,212,000 against a ₹602,000 median for Roads & Paving works in PALWAL (101% above, 78 peer works)
- 565 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹12.12 L | MEDIUM 59 | |
| 3 | Interlocking tiles baniya ki haweli to bada mandir Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹1,361,000 against a ₹602,000 median for Roads & Paving works in PALWAL (126% above, 78 peer works)
- 565 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹13.61 L | MEDIUM 59 | |
| 4 | Construction of rasta PWD road to Mandkola (Silani wali) to Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹2,155,000 against a ₹602,000 median for Roads & Paving works in PALWAL (258% above, 78 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹21.55 L | MEDIUM 59 | |
| 5 | Construction of rasta PWD road (Akbarpur Natol) to Chavad De Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹1,359,000 against a ₹602,000 median for Roads & Paving works in PALWAL (126% above, 78 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹13.59 L | MEDIUM 59 | |
| 6 | Construction of Rasta Nuh PWD road to Mata mandir (Kakad wal Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹1,778,000 against a ₹602,000 median for Roads & Paving works in PALWAL (195% above, 78 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹17.78 L | MEDIUM 59 | |
| 7 | Construction of rasta kalsada road to Primary school village Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹2,033,000 against a ₹602,000 median for Roads & Paving works in PALWAL (238% above, 78 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹20.33 L | MEDIUM 59 | |
| 8 | Construction of rasta Phirni to Hanuman Mandir village Hudit Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹1,824,000 against a ₹602,000 median for Roads & Paving works in PALWAL (203% above, 78 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹18.24 L | MEDIUM 59 | |
| 9 | Construction of rasta from Chattar s/o Sukhram house to Goli Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹2,040,000 against a ₹602,000 median for Roads & Paving works in PALWAL (239% above, 78 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹20.40 L | MEDIUM 59 | |
| 10 | Interlocking of tiles h/o Ashok to h/o Pappu and interlockin Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹1,803,000 against a ₹602,000 median for Roads & Paving works in PALWAL (200% above, 78 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹18.03 L | MEDIUM 59 | |
| 11 | Interlocking of Tiles h/o Prakash to h/o Omkar Street Lighting — PALWAL(CEO DRDA MPLADS PALWAL) - ₹1,319,000 against a ₹358,872 median for Street Lighting works in PALWAL (268% above, 20 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹13.19 L | MEDIUM 59 | |
| 12 | Pavement of IPB rasta in BPL colony (2 no street) Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹1,621,000 against a ₹602,000 median for Roads & Paving works in PALWAL (169% above, 78 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹16.21 L | MEDIUM 59 | |
| 13 | Construction of IPB rasta from Badha-Maheshpur road to Chand Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹2,148,000 against a ₹602,000 median for Roads & Paving works in PALWAL (257% above, 78 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹21.48 L | MEDIUM 59 | |
| 14 | Construction of rasta Suleman house to water buster Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹1,145,000 against a ₹602,000 median for Roads & Paving works in PALWAL (90% above, 78 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹11.45 L | MEDIUM 56 | |
| 15 | Construction of hall in community centre, Gorrilla Mohalla P Community Buildings — PALWAL(CEO DRDA MPLADS PALWAL) - ₹1,889,000 against a ₹1,003,500 median for Community Buildings works in PALWAL (88% above, 30 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹18.89 L | MEDIUM 56 | |
| 16 | Interlocking of tiles of h/o Changa singh to h/o Shamshan Gh Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹1,110,000 against a ₹602,000 median for Roads & Paving works in PALWAL (84% above, 78 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹11.10 L | MEDIUM 55 | |
| 17 | Construction of rasta Kirenapl s/o Gyashi house to Khad Goda Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹1,008,000 against a ₹602,000 median for Roads & Paving works in PALWAL (67% above, 78 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹10.08 L | MEDIUM 50 | |
| 18 | Construction of IPB rasta from Mahipal s/o Rohan lal to Indr Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹1,006,000 against a ₹602,000 median for Roads & Paving works in PALWAL (67% above, 78 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹10.06 L | MEDIUM 50 | |
| 19 | Interlocking of tiles from H/o Hukam Pal to H/o Chattarpal P Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹1,000,000 against a ₹602,000 median for Roads & Paving works in PALWAL (66% above, 78 peer works)
- 553 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹10.00 L | MEDIUM 50 | |
| 20 | Interlocking of tiles from nale ki firni to Shiv Mukhteshwer Roads & Paving — PALWAL(CEO DRDA MPLADS PALWAL) - ₹1,000,000 against a ₹602,000 median for Roads & Paving works in PALWAL (66% above, 78 peer works)
- 554 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹10.00 L | MEDIUM 50 | |
| 21 | Construction of Shed in Bharat Ghar in Kishori Mohala Community Buildings — PALWAL(CEO DRDA MPLADS PALWAL) - ₹1,552,000 against a ₹1,003,500 median for Community Buildings works in PALWAL (55% above, 30 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹15.52 L | MEDIUM 49 | |
| 22 | Construction of Panchal Bhawan Community Buildings — PALWAL(CEO DRDA MPLADS PALWAL) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹13.51 L | MEDIUM 48 | |
| 23 | Const. of Choupal Balmiki Choupal Village Ahrawan Community Buildings — PALWAL(CEO DRDA MPLADS PALWAL) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 565 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹12.00 L | MEDIUM 47 | |
| 24 | Construction of Shed in SC community center Community Buildings — PALWAL(CEO DRDA MPLADS PALWAL) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹11.72 L | MEDIUM 47 | |
| 25 | Construction of Jogi Chaupal Community Buildings — PALWAL(CEO DRDA MPLADS PALWAL) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 568 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| PALWAL | ₹11.50 L | MEDIUM 47 | |