Construction of Shed in Bharat Ghar in Kishori Mohala
Community Buildings
Haryana / PALWAL — PALWAL(CEO DRDA MPLADS PALWAL) · Krishan Pal Gurjar (FARIDABAD)
Overall risk score
49/100
Blended from the five components below, each weighted as shown.
Risk components
Cost60
Delay100
Duplication0
Agency57
Compliance0
Sanctioned
₹15.52 L
Delay
568d
Cost deviation
55%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹1,552,000 against a ₹1,003,500 median for Community Buildings works in PALWAL (55% above, 30 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 568 days beyond expected completionPublished dates
- Implementing agency has a 57% delay rate across its projectsStated compliance rule
Decision trail
Nobody has recorded a decision on this work yet.