| 1 | Road Concreting Work (C.C Road), Cherangala Village, Bhagama Roads & Paving — KODAGU(Deputy Commsioner Kodagu_ida) - ₹1,000,000 against a ₹400,000 median for Roads & Paving works in KODAGU (150% above, 26 peer works)
- 406 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 2 | Road Concreting Work (C.C Road), Cherangala Village, Bhagama Roads & Paving — KODAGU(Deputy Commsioner Kodagu_ida) - ₹1,000,000 against a ₹400,000 median for Roads & Paving works in KODAGU (150% above, 26 peer works)
- 406 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 62% of this agency's ₹48,287,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 3 vendors and 63 transactions
| KODAGU | ₹10.00 L | HIGH 83
cost 25delay 25duplication 20 | |
| 3 | Construction of K.Badaga Vividodesha Prathamika Krushi Grami Community Buildings — KODAGU(Deputy Commsioner Kodagu_ida) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KODAGU (100% above, 73 peer works)
- 245 days beyond expected completion
Read more (1 more)Show less- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹10.00 L | MEDIUM 65 | |
| 4 | Construction of Sports Training Centre Admin Block Ground Fl Sports — KODAGU(Deputy Commsioner Kodagu_ida) - ₹19,900,000 against a ₹2,000,000 median for Sports works in KODAGU (895% above, 9 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹1.99 Cr | MEDIUM 60
cost 25duplication 20agency 15 | |
| 5 | Construction of Sports Training Centre Sports — KODAGU(Deputy Commsioner Kodagu_ida) - ₹19,950,000 against a ₹2,000,000 median for Sports works in KODAGU (898% above, 9 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹2.00 Cr | MEDIUM 60
cost 25duplication 20agency 15 | |
| 6 | Construction of Sports Training Centre Admin Block Ground Fl Sports — KODAGU(Deputy Commsioner Kodagu_ida) - ₹19,900,000 against a ₹2,000,000 median for Sports works in KODAGU (895% above, 9 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 62% of this agency's ₹48,287,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 3 vendors and 63 transactions
| KODAGU | ₹1.99 Cr | MEDIUM 58
cost 25duplication 20agency 13 | |
| 7 | Construction of Sports Training Centre Sports — KODAGU(Deputy Commsioner Kodagu_ida) - ₹19,950,000 against a ₹2,000,000 median for Sports works in KODAGU (898% above, 9 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 62% of this agency's ₹48,287,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 3 vendors and 63 transactions
| KODAGU | ₹2.00 Cr | MEDIUM 58
cost 25duplication 20agency 13 | |
| 8 | Purchase Books for Court Library Madikeri. Education — KODAGU(Deputy Commsioner Kodagu_ida) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 264 days beyond expected completion
Read more (1 more)Show less- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹50,000 | MEDIUM 50 | |
| 9 | Further Construction of Bharathiya Sarvananika Bhavana. Community Buildings — KODAGU(Deputy Commsioner Kodagu_ida) - 264 days beyond expected completion
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹4.00 L | MEDIUM 48 | |
| 10 | Continued work of Gonikoppa High School Auditorium. Education — KODAGU(Deputy Commsioner Kodagu_ida) - 264 days beyond expected completion
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹4.00 L | MEDIUM 48 | |
| 11 | Construction of Bhagavathi temple Community Hall Community Buildings — KODAGU(Deputy Commsioner Kodagu_ida) - 264 days beyond expected completion
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹4.00 L | MEDIUM 48 | |
| 12 | Construction of Sastavu Community hall Community Buildings — KODAGU(Deputy Commsioner Kodagu_ida) - 264 days beyond expected completion
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹4.00 L | MEDIUM 48 | |
| 13 | Samudaya Bhavana at Sampaje village Sri. Panhalingeshwara Te Religious & Cultural — KODAGU(Deputy Commsioner Kodagu_ida) - 264 days beyond expected completion
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹4.00 L | MEDIUM 48 | |
| 14 | Construction of Retaining wall to flood control. Boundary & Protection — KODAGU(Deputy Commsioner Kodagu_ida) - 264 days beyond expected completion
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹4.00 L | MEDIUM 48 | |
| 15 | Construction of Dasoha BHavan Community Buildings — KODAGU(Deputy Commsioner Kodagu_ida) - 264 days beyond expected completion
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹5.00 L | MEDIUM 48 | |
| 16 | Construction of Road from the house of Gopalaswamy to Give V Roads & Paving — KODAGU(Deputy Commsioner Kodagu_ida) - 264 days beyond expected completion
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹5.00 L | MEDIUM 48 | |
| 17 | Continuation work of Garvale Kodavasamaja. Community Buildings — KODAGU(Deputy Commsioner Kodagu_ida) - 264 days beyond expected completion
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹5.00 L | MEDIUM 48 | |
| 18 | Continuation work of Basaveshwara Community Hall Community Buildings — KODAGU(Deputy Commsioner Kodagu_ida) - 264 days beyond expected completion
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹5.00 L | MEDIUM 48 | |
| 19 | Continued work of SMDP Samudaya Bhavan Community Buildings — KODAGU(Deputy Commsioner Kodagu_ida) - 264 days beyond expected completion
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹5.00 L | MEDIUM 48 | |
| 20 | Construction of Birunani village PAnchyathi building. Community Buildings — KODAGU(Deputy Commsioner Kodagu_ida) - 264 days beyond expected completion
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹5.00 L | MEDIUM 48 | |
| 21 | Continuation work of Krishna Temple Religious & Cultural — KODAGU(Deputy Commsioner Kodagu_ida) - 264 days beyond expected completion
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹5.00 L | MEDIUM 48 | |
| 22 | Construction of Kote Mariyamma Community hall. Community Buildings — KODAGU(Deputy Commsioner Kodagu_ida) - 264 days beyond expected completion
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹5.00 L | MEDIUM 48 | |
| 23 | Construction of Kendra Kodava Samaja. Community Buildings — KODAGU(Deputy Commsioner Kodagu_ida) - 264 days beyond expected completion
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹5.00 L | MEDIUM 48 | |
| 24 | Community Hall Construction Community Buildings — KODAGU(Deputy Commsioner Kodagu_ida) - 264 days beyond expected completion
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹5.00 L | MEDIUM 48 | |
| 25 | Renovation of post office Community Buildings — KODAGU(Deputy Commsioner Kodagu_ida) - 264 days beyond expected completion
- 91% of this agency's ₹48,562,000 spend went to one vendor (Kodagu Nirmithi Kendra), across 4 vendors and 47 transactions
| KODAGU | ₹2.00 L | MEDIUM 48 | |