60 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | KODAGU(Deputy Commsioner Kodagu_ida) 1 high risk | 60 | 0 | ₹7.50 Cr | 32 | 34.9 | Kodagu Nirmithi Kendra 91% of spend · 4 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Yaduveer Wadiyar MYSORE | 55 | ₹3.25 Cr | 29 |
| Ajay Makan Sitting Rajya Sabha | 2 | ₹3.99 Cr | 2 |
| G.C. Chandrashekhar Sitting Rajya Sabha | 2 | ₹17.00 L | 0 |
| Jaggesh Sitting Rajya Sabha | 1 | ₹10.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 34 | ₹2.12 Cr | 20 |
| Roads & Paving | 5 | ₹34.00 L | 3 |
| Education | 5 | ₹19.50 L | 3 |
| Boundary & Protection | 4 | ₹21.00 L | 1 |
| Other | 3 | ₹14.00 L | 0 |
| Sports | 3 | ₹4.19 Cr | 2 |
| Religious & Cultural | 2 | ₹9.00 L | 2 |
| Equipment & Vehicles | 2 | ₹13.00 L | 1 |
| Drainage & Sanitation | 1 | ₹4.00 L | 0 |
| Street Lighting | 1 | ₹5.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Road Concreting Work (C.C Road), Cherangala Village, Bhagama ₹1,000,000 against a ₹400,000 median for Roads & Paving works in KODAGU (150% above, 26 peer works) | KODAGU(Deputy Commsioner Kodagu_ida) | Recommended | ₹10.00 L | 406 d | +150% | 85.0 | HIGH |
| Construction of K.Badaga Vividodesha Prathamika Krushi Grami ₹1,000,000 against a ₹500,000 median for Community Buildings works in KODAGU (100% above, 73 peer works) | KODAGU(Deputy Commsioner Kodagu_ida) | Recommended | ₹10.00 L | 245 d | +100% | 65.0 | MEDIUM |
| Construction of Sports Training Centre Admin Block Ground Fl ₹19,900,000 against a ₹2,000,000 median for Sports works in KODAGU (895% above, 9 peer works) | KODAGU(Deputy Commsioner Kodagu_ida) | Recommended | ₹1.99 Cr | — | +895% | 60.0 | MEDIUM |
| Construction of Sports Training Centre ₹19,950,000 against a ₹2,000,000 median for Sports works in KODAGU (898% above, 9 peer works) | KODAGU(Deputy Commsioner Kodagu_ida) | Recommended | ₹2.00 Cr | — | +898% | 60.0 | MEDIUM |
| Purchase Books for Court Library Madikeri. Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | KODAGU(Deputy Commsioner Kodagu_ida) | Recommended | ₹50,000 | 264 d | -90% | 50.3 | MEDIUM |
| Further Construction of Bharathiya Sarvananika Bhavana. 264 days beyond expected completion | KODAGU(Deputy Commsioner Kodagu_ida) | Recommended | ₹4.00 L | 264 d | -20% | 48.4 | MEDIUM |
| Continued work of Gonikoppa High School Auditorium. 264 days beyond expected completion | KODAGU(Deputy Commsioner Kodagu_ida) | Recommended | ₹4.00 L | 264 d | -20% | 48.4 | MEDIUM |
| Construction of Bhagavathi temple Community Hall 264 days beyond expected completion | KODAGU(Deputy Commsioner Kodagu_ida) | Recommended | ₹4.00 L | 264 d | -20% | 48.4 | MEDIUM |
| Construction of Sastavu Community hall 264 days beyond expected completion | KODAGU(Deputy Commsioner Kodagu_ida) | Recommended | ₹4.00 L | 264 d | -20% | 48.4 | MEDIUM |
| Samudaya Bhavana at Sampaje village Sri. Panhalingeshwara Te 264 days beyond expected completion | KODAGU(Deputy Commsioner Kodagu_ida) | Recommended | ₹4.00 L | 264 d | 0% | 48.4 | MEDIUM |
| Construction of Retaining wall to flood control. 264 days beyond expected completion | KODAGU(Deputy Commsioner Kodagu_ida) | Recommended | ₹4.00 L | 264 d | 0% | 48.4 | MEDIUM |
| Construction of Dasoha BHavan 264 days beyond expected completion | KODAGU(Deputy Commsioner Kodagu_ida) | Recommended | ₹5.00 L | 264 d | 0% | 48.0 | MEDIUM |
| Construction of Road from the house of Gopalaswamy to Give V 264 days beyond expected completion | KODAGU(Deputy Commsioner Kodagu_ida) | Recommended | ₹5.00 L | 264 d | +25% | 48.0 | MEDIUM |
| Continuation work of Garvale Kodavasamaja. 264 days beyond expected completion | KODAGU(Deputy Commsioner Kodagu_ida) | Recommended | ₹5.00 L | 264 d | 0% | 48.0 | MEDIUM |
| Continuation work of Basaveshwara Community Hall 264 days beyond expected completion | KODAGU(Deputy Commsioner Kodagu_ida) | Recommended | ₹5.00 L | 264 d | 0% | 48.0 | MEDIUM |