| 1 | construction of cultural hall Community Buildings — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in KALABURAGI (150% above, 105 peer works)
- 141 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹10.00 L | HIGH 73
cost 25duplication 20delay 20 | |
| 2 | Construction of CC Road from Hanuman Temple to PDA Engineeri Roads & Paving — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹8,700,000 against a ₹499,000 median for Roads & Paving works in KALABURAGI (1643% above, 101 peer works)
- 119 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹87.00 L | HIGH 70
cost 25duplication 20delay 17 | |
| 3 | Construction of CC Road from Hanuman Temple to PDA Engineeri Roads & Paving — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹8,700,000 against a ₹499,000 median for Roads & Paving works in KALABURAGI (1643% above, 101 peer works)
- 119 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹87.00 L | HIGH 70
cost 25duplication 20delay 17 | |
| 4 | Construction of Sanskrut Bhawan/ cultural hall near Shri Sh Community Buildings — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in KALABURAGI (150% above, 105 peer works)
- 680 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹10.00 L | MEDIUM 66 | |
| 5 | Installation of highmast at Deval Ganagapur -2 village of Af Street Lighting — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 762 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹5.55 L | MEDIUM 66
delay 25duplication 19cost 13 | |
| 6 | Installation of Highmast at Deval Ganagapur -1 Village of Af Street Lighting — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 762 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹5.55 L | MEDIUM 66
delay 25duplication 19cost 13 | |
| 7 | Construction of Sanskrut Bhawan/ cultural hall near Shri Sha Community Buildings — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in KALABURAGI (150% above, 105 peer works)
- 680 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹10.00 L | MEDIUM 63 | |
| 8 | Construction of toilet block for boys at ground floor of De Roads & Paving — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 731 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹4.99 L | MEDIUM 62
delay 25duplication 17cost 11 | |
| 9 | Construction of toilet block for Boys at 1st floor of Deva Roads & Paving — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 731 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹4.99 L | MEDIUM 62
delay 25duplication 17cost 11 | |
| 10 | Construction of toilet block for girls at ground floor of De Roads & Paving — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 731 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹4.99 L | MEDIUM 62
delay 25duplication 17cost 11 | |
| 11 | Construction of toilet block for Girls at 1st floor of Dev Roads & Paving — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 731 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹4.99 L | MEDIUM 62
delay 25duplication 17cost 11 | |
| 12 | Construction of Sanskrit Bhawan near Sri Rachoteshwar Math a Community Buildings — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in KALABURAGI (150% above, 105 peer works)
- 552 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹10.00 L | MEDIUM 59 | |
| 13 | Construction of Sanskrit Bhawan at Shree Burubhamlingeshwar Community Buildings — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in KALABURAGI (150% above, 105 peer works)
- 552 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹10.00 L | MEDIUM 59 | |
| 14 | CC Road Chandapur Main Road to Gandi Meshappa Near Kadtal Ta Roads & Paving — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹1,500,000 against a ₹499,000 median for Roads & Paving works in KALABURAGI (201% above, 101 peer works)
- 585 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹15.00 L | MEDIUM 59 | |
| 15 | Construction of Shed near Shri Shivasharan Ambigara Chowdayy Community Buildings — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in KALABURAGI (150% above, 105 peer works)
- 622 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹10.00 L | MEDIUM 59 | |
| 16 | Construction of School room at Vidyaniketan English Medium Roads & Paving — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹1,000,000 against a ₹499,000 median for Roads & Paving works in KALABURAGI (100% above, 101 peer works)
- 646 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹10.00 L | MEDIUM 59 | |
| 17 | Providing Furniture to Bar Association Chincholi Chincholi T Equipment & Vehicles — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹200,000 against a ₹97,865 median for Equipment & Vehicles works in KALABURAGI (104% above, 8 peer works)
- 658 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹2.00 L | MEDIUM 59 | |
| 18 | Construction of Sanskrut Bhawan near Sri Mahasadvi Hemreddy Community Buildings — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in KALABURAGI (150% above, 105 peer works)
- 666 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹10.00 L | MEDIUM 59 | |
| 19 | Construction of Sanskrit Bhawan near Kudalasangam Temple of Community Buildings — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹5,000,000 against a ₹400,000 median for Community Buildings works in KALABURAGI (1150% above, 105 peer works)
- 666 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹50.00 L | MEDIUM 59 | |
| 20 | Construction of Sanskrut Bhawan/ cultural hall near Ekdandi Community Buildings — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in KALABURAGI (150% above, 105 peer works)
- 680 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹10.00 L | MEDIUM 59 | |
| 21 | Construction of Crematoriums or structures on burial/ cremat Equipment & Vehicles — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹5,500,000 against a ₹97,865 median for Equipment & Vehicles works in KALABURAGI (5520% above, 8 peer works)
- 680 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹55.00 L | MEDIUM 59 | |
| 22 | Construction of Samudaya Bhawan / Community centre at Shree Community Buildings — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹2,500,000 against a ₹400,000 median for Community Buildings works in KALABURAGI (525% above, 105 peer works)
- 690 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹25.00 L | MEDIUM 59 | |
| 23 | CC Road and Drainage from Social welfare office to Excise De Roads & Paving — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹1,000,000 against a ₹499,000 median for Roads & Paving works in KALABURAGI (100% above, 101 peer works)
- 734 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹10.00 L | MEDIUM 59 | |
| 24 | Koranti Hanuman Temple Religious & Cultural — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹555,000 against a ₹97,865 median for Religious & Cultural works in KALABURAGI (467% above, 22 peer works)
- 760 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹5.55 L | MEDIUM 59 | |
| 25 | Sai Mandir Sainagar Religious & Cultural — KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) - ₹555,000 against a ₹97,865 median for Religious & Cultural works in KALABURAGI (467% above, 22 peer works)
- 760 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 58% delay rate across its projects
| KALABURAGI | ₹5.55 L | MEDIUM 59 | |