59 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) 2 high risk | 59 | 1 | ₹13.79 Cr | 21 | 37.5 | SIDDARAM BELKOTI 28% of spend · 10 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Sagar Eshwar Khandre BIDAR | 30 | ₹2.03 Cr | 18 |
| Radhakrishna GULBARGA | 26 | ₹9.60 Cr | 0 |
| Syed Naseer Hussain Sitting Rajya Sabha | 2 | ₹1.68 Cr | 2 |
| Nirmala Sitharaman Sitting Rajya Sabha | 1 | ₹48.23 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 22 | ₹2.17 Cr | 14 |
| Education | 19 | ₹7.74 Cr | 0 |
| Roads & Paving | 11 | ₹2.23 Cr | 7 |
| Drainage & Sanitation | 2 | ₹20.00 L | 0 |
| Street Lighting | 1 | ₹25.00 L | 0 |
| Water | 1 | ₹4.99 L | 0 |
| Other | 1 | ₹4.99 L | 0 |
| Religious & Cultural | 1 | ₹10.00 L | 0 |
| Sports | 1 | ₹1.00 Cr | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| construction of cultural hall ₹1,000,000 against a ₹400,000 median for Community Buildings works in KALABURAGI (150% above, 105 peer works) | KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) | Recommended | ₹10.00 L | 141 d | +150% | 73.3 | HIGH |
| Construction of CC Road from Hanuman Temple to PDA Engineeri ₹8,700,000 against a ₹499,000 median for Roads & Paving works in KALABURAGI (1643% above, 101 peer works) | KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) | Recommended | ₹87.00 L | 119 d | +1643% | 70.3 | HIGH |
| Construction of C.C Road from SVP Chowk to PDA Engineering c ₹8,100,000 against a ₹499,000 median for Roads & Paving works in KALABURAGI (1523% above, 101 peer works) | KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) | Recommended | ₹81.00 L | 30 d | +1523% | 57.9 | MEDIUM |
| construction of cc road 141 days beyond expected completion | KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) | Recommended | ₹6.00 L | 141 d | +20% | 55.2 | MEDIUM |
| Construction of cultural hall 141 days beyond expected completion | KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) | Recommended | ₹4.99 L | 141 d | +25% | 54.5 | MEDIUM |
| construction of cultural hall 141 days beyond expected completion | KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) | Recommended | ₹4.99 L | 141 d | +25% | 54.5 | MEDIUM |
| construction of cultural hall 141 days beyond expected completion | KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) | Recommended | ₹4.99 L | 141 d | +25% | 54.5 | MEDIUM |
| construction of cultural hall 141 days beyond expected completion | KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) | Recommended | ₹4.99 L | 141 d | +25% | 54.5 | MEDIUM |
| construction of cultural hall 141 days beyond expected completion | KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) | Recommended | ₹4.99 L | 141 d | +25% | 54.5 | MEDIUM |
| construction of cultural hall 141 days beyond expected completion | KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) | Recommended | ₹4.99 L | 141 d | +25% | 54.5 | MEDIUM |
| construction of cultural hall 141 days beyond expected completion | KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) | Recommended | ₹4.99 L | 141 d | +25% | 54.5 | MEDIUM |
| construction of cultural hall 141 days beyond expected completion | KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) | Recommended | ₹4.99 L | 141 d | +25% | 54.5 | MEDIUM |
| construction of cultural hall 141 days beyond expected completion | KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) | Recommended | ₹4.99 L | 141 d | +25% | 54.5 | MEDIUM |
| construction of cultural hall 141 days beyond expected completion | KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) | Recommended | ₹4.00 L | 141 d | 0% | 54.3 | MEDIUM |
| construction of cc road 141 days beyond expected completion | KALABURAGI(DEPUTY COMMISSIONER GULBARGA_IDA) | Recommended | ₹4.00 L | 141 d | -20% | 54.3 | MEDIUM |