| 1 | Construction of two class rooms in Bhagwat Jha Azad Degree C Education — JAMTARA(Deputy Commissioner Jamtara_IDA) - ₹1,000,000 against a ₹249,745 median for Education works in JAMTARA (300% above, 46 peer works)
- 430 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 97% of this agency's ₹28,850,000 spend went to one vendor (PRAHLAD MANDAL), across 2 vendors and 108 transactions
| JAMTARA | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 2 | Construction of two class rooms in Bhagwat Jha Azad Degree C Education — JAMTARA(Deputy Commissioner Jamtara_IDA) - ₹1,000,000 against a ₹249,745 median for Education works in JAMTARA (300% above, 46 peer works)
- 430 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 46% of this agency's ₹28,689,800 spend went to one vendor (SANTOSH KUMAR MONDAL), across 3 vendors and 104 transactions
| JAMTARA | ₹10.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 3 | Construction of Community Building in Rajamdih CowShed Community Buildings — JAMTARA(Deputy Commissioner Jamtara_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in JAMTARA (67% above, 12 peer works)
- 614 days beyond expected completion
Read more (1 more)Show less- 97% of this agency's ₹28,850,000 spend went to one vendor (PRAHLAD MANDAL), across 2 vendors and 108 transactions
| JAMTARA | ₹5.00 L | MEDIUM 57 | |
| 4 | Renovation of Bharat Mata Chauk Roads & Paving — JAMTARA(Deputy Commissioner Jamtara_IDA) - 614 days beyond expected completion
- 97% of this agency's ₹28,850,000 spend went to one vendor (PRAHLAD MANDAL), across 2 vendors and 108 transactions
| JAMTARA | ₹2.50 L | MEDIUM 47 | |
| 5 | Construction of Shade of Bhara Mata Religious & Cultural — JAMTARA(Deputy Commissioner Jamtara_IDA) - 614 days beyond expected completion
- 97% of this agency's ₹28,850,000 spend went to one vendor (PRAHLAD MANDAL), across 2 vendors and 108 transactions
| JAMTARA | ₹2.50 L | MEDIUM 47 | |
| 6 | Renovation of Theater Hall Community Buildings — JAMTARA(Deputy Commissioner Jamtara_IDA) - 614 days beyond expected completion
- 97% of this agency's ₹28,850,000 spend went to one vendor (PRAHLAD MANDAL), across 2 vendors and 108 transactions
| JAMTARA | ₹2.50 L | MEDIUM 47 | |
| 7 | Construction of PCC Road from Panchanan Mahto's Farm to Sude Roads & Paving — JAMTARA(Deputy Commissioner Jamtara_IDA) - 614 days beyond expected completion
- 97% of this agency's ₹28,850,000 spend went to one vendor (PRAHLAD MANDAL), across 2 vendors and 108 transactions
| JAMTARA | ₹2.50 L | MEDIUM 47 | |
| 8 | Construction of PCC Road from Karo Road Sri Bhagwat Pandit's Roads & Paving — JAMTARA(Deputy Commissioner Jamtara_IDA) - 614 days beyond expected completion
- 97% of this agency's ₹28,850,000 spend went to one vendor (PRAHLAD MANDAL), across 2 vendors and 108 transactions
| JAMTARA | ₹2.50 L | MEDIUM 47 | |
| 9 | Construction of Burial Shade near Shila River Religious & Cultural — JAMTARA(Deputy Commissioner Jamtara_IDA) - 614 days beyond expected completion
- 97% of this agency's ₹28,850,000 spend went to one vendor (PRAHLAD MANDAL), across 2 vendors and 108 transactions
| JAMTARA | ₹3.00 L | MEDIUM 47 | |
| 10 | Construction of Shed beside Ajay River Community Buildings — JAMTARA(Deputy Commissioner Jamtara_IDA) - 614 days beyond expected completion
- 97% of this agency's ₹28,850,000 spend went to one vendor (PRAHLAD MANDAL), across 2 vendors and 108 transactions
| JAMTARA | ₹3.00 L | MEDIUM 47 | |
| 11 | Construction of Burial Shed Community Buildings — JAMTARA(Deputy Commissioner Jamtara_IDA) - 614 days beyond expected completion
- 97% of this agency's ₹28,850,000 spend went to one vendor (PRAHLAD MANDAL), across 2 vendors and 108 transactions
| JAMTARA | ₹3.00 L | MEDIUM 47 | |