Construction of Community Building in Rajamdih CowShed

Community Buildings

Jharkhand / JAMTARA — JAMTARA(Deputy Commissioner Jamtara_IDA) · Sunil Soren (DUMKA)

Overall risk score
57/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost67
Delay100
Duplication0
Agency100
Compliance0
Sanctioned
₹5.00 L
Delay
614d
Cost deviation
67%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹500,000 against a ₹300,000 median for Community Buildings works in JAMTARA (67% above, 12 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 614 days beyond expected completionPublished dates
  • 97% of this agency's ₹28,850,000 spend went to one vendor (PRAHLAD MANDAL), across 2 vendors and 108 transactionsStatistics · Herfindahl-Hirschman index

Decision trail

Nobody has recorded a decision on this work yet.