| 1 | Development of Swargodeo Chaulung Statue and Park at Tipam Religious & Cultural — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹5,000,000 against a ₹500,000 median for Religious & Cultural works in DIBRUGARH (900% above, 41 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹50.00 L | MEDIUM 62
cost 25duplication 20agency 12 | |
| 2 | Development of Swargodeo Chaulung Statue and Park at Tipam Religious & Cultural — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹5,000,000 against a ₹500,000 median for Religious & Cultural works in DIBRUGARH (900% above, 41 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹50.00 L | MEDIUM 62
cost 25duplication 20agency 12 | |
| 3 | Construction of Culture Centre near Tingrai Chariali Durga M Religious & Cultural — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in DIBRUGARH (100% above, 41 peer works)
- 551 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 62 | |
| 4 | Development of Cultural Centre near Nemupather Siv Mandir, P Religious & Cultural — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in DIBRUGARH (100% above, 41 peer works)
- 551 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 62 | |
| 5 | Haladhibari Chaolkara Gaon Cultural Centre Religious & Cultural — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in DIBRUGARH (100% above, 41 peer works)
- 618 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 62 | |
| 6 | Teliapather Punya Aranya Cultural Center Religious & Cultural — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in DIBRUGARH (100% above, 41 peer works)
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 62 | |
| 7 | Infrastructure development of Naharkatia Bihu Mancha Phase-I Religious & Cultural — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹1,500,000 against a ₹500,000 median for Religious & Cultural works in DIBRUGARH (200% above, 41 peer works)
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹15.00 L | MEDIUM 62 | |
| 8 | Construction of Tai Vakha and Cultural Centre at Dhekeri Gao Community Buildings — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹2,000,000 against a ₹1,000,000 median for Community Buildings works in DIBRUGARH (100% above, 49 peer works)
- 212 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹20.00 L | MEDIUM 62 | |
| 9 | Construction of SHG Market Complex for women at Ward no 5, 2 Community Buildings — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹3,000,000 against a ₹1,000,000 median for Community Buildings works in DIBRUGARH (200% above, 49 peer works)
- 223 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹30.00 L | MEDIUM 62 | |
| 10 | Construction of auditorium, Nagaon Tiniali at Hajuapathar ga Community Buildings — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹2,500,000 against a ₹1,000,000 median for Community Buildings works in DIBRUGARH (150% above, 49 peer works)
- 223 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹25.00 L | MEDIUM 62 | |
| 11 | Construction of Cultural center near Kunda Ata Than at 3 no. Religious & Cultural — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in DIBRUGARH (100% above, 41 peer works)
- 223 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 62 | |
| 12 | Construction of market Cpmplex at LahowalSamabai Samity Land Community Buildings — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹2,000,000 against a ₹1,000,000 median for Community Buildings works in DIBRUGARH (100% above, 49 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹20.00 L | MEDIUM 57
cost 25duplication 20agency 12 | |
| 13 | Construction of market Cpmplex at LahowalSamabai Samity Land Community Buildings — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹2,000,000 against a ₹1,000,000 median for Community Buildings works in DIBRUGARH (100% above, 49 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹20.00 L | MEDIUM 57
cost 25duplication 20agency 12 | |
| 14 | Infrastructure development of Joypur Forest Park Sports — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹25.00 L | MEDIUM 54 | |
| 15 | Infrastructure development of Tipam Sukafa Park Sports — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹25.00 L | MEDIUM 54 | |
| 16 | Installation of CCTV in Chabua Muncipality with central acce Equipment & Vehicles — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 212 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹25.00 L | MEDIUM 52 | |
| 17 | Construction of Ashok Path bye-lane-3 Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹12.00 L | MEDIUM 52 | |
| 18 | Infrastructure development of Public Auditorium at Moran TE Community Buildings — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹1,500,000 against a ₹1,000,000 median for Community Buildings works in DIBRUGARH (50% above, 49 peer works)
- 618 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹15.00 L | MEDIUM 52 | |
| 19 | Construction of Nagakhelia Path Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 51 | |
| 20 | Construction of Baruah Pather Bye-Lane Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 51 | |
| 21 | Construction of Sashan Para bye-lane, near Dr. J. Dutta(R) Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 51 | |
| 22 | Construction of Jeuti Path Bye-Lane near Adv. Goswami(R) Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 51 | |
| 23 | Construction of Nandanpur Path Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 51 | |
| 24 | Construction of Boiragimoth bye-lane Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 51 | |
| 25 | Construction of Chapori Path bye-lane Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 51 | |