Construction of SHG Market Complex for women at Ward no 5, 2
Community Buildings
Assam / DIBRUGARH — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) · Sarbananda Sonowal (DIBRUGARH)
Construction of SHG Market Complex for women at Ward no 5, 2 no. Naoholiagaon
Overall risk score
62/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency77
Compliance0
Sanctioned
₹30.00 L
Delay
223d
Cost deviation
200%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹3,000,000 against a ₹1,000,000 median for Community Buildings works in DIBRUGARH (200% above, 49 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 223 days beyond expected completionPublished dates
- Implementing agency has a 77% delay rate across its projectsStated compliance rule
Decision trail
Nobody has recorded a decision on this work yet.