| 1 | Construction of Community hall Community Buildings — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹1,000,000 against a ₹499,000 median for Community Buildings works in CHIKKABALLAPURA (100% above, 56 peer works)
- 600 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 2 | Road Development Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKABALLAPURA (100% above, 36 peer works)
- 610 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 3 | Road Development Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹1,200,000 against a ₹500,000 median for Roads & Paving works in CHIKKABALLAPURA (140% above, 36 peer works)
- 610 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹12.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 4 | Road Development Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹900,000 against a ₹500,000 median for Roads & Paving works in CHIKKABALLAPURA (80% above, 36 peer works)
- 610 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹9.00 L | HIGH 71
delay 25cost 20duplication 20 | |
| 5 | Construction of Dr.B.R.Ambedkar Samudaya Bavana at Sidlaghat Community Buildings — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹5,000,000 against a ₹499,000 median for Community Buildings works in CHIKKABALLAPURA (902% above, 56 peer works)
- 180 days beyond expected completion
Read more (1 more)Show less- 67% of this agency's ₹26,337,696 spend went to one vendor (Project Manager), across 22 vendors and 77 transactions
| CHIKKABALLAPURA | ₹50.00 L | MEDIUM 61 | |
| 6 | Construction of bus-sheds at Chikkaballapur(T) Near MDR Road Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKABALLAPURA (100% above, 36 peer works)
- 273 days beyond expected completion
Read more (1 more)Show less- 67% of this agency's ₹26,337,696 spend went to one vendor (Project Manager), across 22 vendors and 77 transactions
| CHIKKABALLAPURA | ₹10.00 L | MEDIUM 61 | |
| 7 | Construction of bus-sheds at Chikkaballapur beechaganahalli Community Buildings — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹1,000,000 against a ₹499,000 median for Community Buildings works in CHIKKABALLAPURA (100% above, 56 peer works)
- 273 days beyond expected completion
Read more (1 more)Show less- 67% of this agency's ₹26,337,696 spend went to one vendor (Project Manager), across 22 vendors and 77 transactions
| CHIKKABALLAPURA | ₹10.00 L | MEDIUM 61 | |
| 8 | Construction of New Building VSSN cooperative society Palyak Community Buildings — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹1,000,000 against a ₹499,000 median for Community Buildings works in CHIKKABALLAPURA (100% above, 56 peer works)
- 273 days beyond expected completion
Read more (1 more)Show less- 67% of this agency's ₹26,337,696 spend went to one vendor (Project Manager), across 22 vendors and 77 transactions
| CHIKKABALLAPURA | ₹10.00 L | MEDIUM 61 | |
| 9 | Construction of bus-sheds at Bagepalli-Chelur road Laghumudd Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKABALLAPURA (100% above, 36 peer works)
- 273 days beyond expected completion
Read more (1 more)Show less- 67% of this agency's ₹26,337,696 spend went to one vendor (Project Manager), across 22 vendors and 77 transactions
| CHIKKABALLAPURA | ₹10.00 L | MEDIUM 61 | |
| 10 | Installation of Hi-Mast Light at Bommekallu Village. Street Lighting — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹499,000 against a ₹250,000 median for Street Lighting works in CHIKKABALLAPURA (100% above, 53 peer works)
- 247 days beyond expected completion
Read more (1 more)Show less- 67% of this agency's ₹26,337,696 spend went to one vendor (Project Manager), across 22 vendors and 77 transactions
| CHIKKABALLAPURA | ₹4.99 L | MEDIUM 61 | |
| 11 | Construction of Hi-Mast Light at Kachahalli Village. Street Lighting — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹495,000 against a ₹250,000 median for Street Lighting works in CHIKKABALLAPURA (98% above, 53 peer works)
- 234 days beyond expected completion
Read more (1 more)Show less- 67% of this agency's ₹26,337,696 spend went to one vendor (Project Manager), across 22 vendors and 77 transactions
| CHIKKABALLAPURA | ₹4.95 L | MEDIUM 60 | |
| 12 | Construction of Bus Stand Community Buildings — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 633 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 13 | CC Road Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 633 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 14 | CC Road Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 633 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 15 | CC Road Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 633 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 16 | Road Development Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 610 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 59
delay 25duplication 20cost 8 | |
| 17 | Road Development Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 610 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 59
delay 25duplication 20cost 8 | |
| 18 | Road Development Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 610 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 59
delay 25duplication 20cost 8 | |
| 19 | Construction of Community Hall Community Buildings — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 610 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 59
delay 25duplication 20cost 8 | |
| 20 | Road Development Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 610 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 59
delay 25duplication 20cost 8 | |
| 21 | Construction of Road and Drain Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKABALLAPURA (100% above, 36 peer works)
- 610 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹10.00 L | MEDIUM 56 | |
| 22 | Construction of first floor for media association Community Buildings — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹1,000,000 against a ₹499,000 median for Community Buildings works in CHIKKABALLAPURA (100% above, 56 peer works)
- 633 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹10.00 L | MEDIUM 56 | |
| 23 | Installing community drinking water plants at Gauribidanur Water — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 234 days beyond expected completion
- 97% similarity with another nearby work
Read more (1 more)Show less- 67% of this agency's ₹26,337,696 spend went to one vendor (Project Manager), across 22 vendors and 77 transactions
| CHIKKABALLAPURA | ₹8.00 L | MEDIUM 56
delay 25duplication 11agency 11 | |
| 24 | High Mask Light Street Lighting — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - Completed work has no photographic documentation on record
- ₹498,803 against a ₹250,000 median for Street Lighting works in CHIKKABALLAPURA (100% above, 53 peer works)
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹4.99 L | MEDIUM 56
cost 25duplication 20agency 6 | |
| 25 | High Mask Light Street Lighting — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - Completed work has no photographic documentation on record
- ₹498,803 against a ₹250,000 median for Street Lighting works in CHIKKABALLAPURA (100% above, 53 peer works)
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹4.99 L | MEDIUM 56
cost 25duplication 20agency 6 | |