| 1 | Renovation of the Chhotka Aahar in village Gerua of Panchaya Water — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹1,200,000 against a ₹200,000 median for Water works in CHATRA (500% above, 156 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹12.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 2 | Renovation of the Chhotka Aahar in village Bukru of Panchaya Water — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹1,000,000 against a ₹200,000 median for Water works in CHATRA (400% above, 156 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 3 | Renovation of the Chhotka Aahar in village Gerua of Panchaya Water — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹1,200,000 against a ₹200,000 median for Water works in CHATRA (500% above, 156 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| CHATRA | ₹12.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 4 | Renovation of the Chhotka Aahar in village Bukru of Panchaya Water — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹1,000,000 against a ₹200,000 median for Water works in CHATRA (400% above, 156 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| CHATRA | ₹10.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 5 | Repairing of Baherwa Ahar Water — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹300,000 against a ₹200,000 median for Water works in CHATRA (50% above, 156 peer works)
- 128 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹3.00 L | MEDIUM 65
duplication 20delay 18agency 15 | |
| 6 | Repairing of Dumaria Ahar Water — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - 115 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹1.00 L | MEDIUM 57
duplication 20delay 16agency 15 | |
| 7 | Construction of community building in Gaurakshani in Gram Pa Community Buildings — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹1,499,500 against a ₹200,000 median for Community Buildings works in CHATRA (650% above, 96 peer works)
- 551 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| CHATRA | ₹15.00 L | MEDIUM 57 | |
| 8 | Construction of community building on the first floor in Gau Community Buildings — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹1,499,000 against a ₹200,000 median for Community Buildings works in CHATRA (650% above, 96 peer works)
- 551 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| CHATRA | ₹14.99 L | MEDIUM 57 | |
| 9 | Design, Fabrication, & Installation of Stainless – Steel Bus Community Buildings — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹9,999,600 against a ₹200,000 median for Community Buildings works in CHATRA (4900% above, 96 peer works)
- 585 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| CHATRA | ₹100.00 L | MEDIUM 57 | |
| 10 | Construction work of guest house in Hattarganj, near Kaulesh Religious & Cultural — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹13,023,225 against a ₹100,000 median for Religious & Cultural works in CHATRA (12923% above, 57 peer works)
- 595 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| CHATRA | ₹1.30 Cr | MEDIUM 57 | |
| 11 | Construction of steps in Purainiya Talab Water — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹600,000 against a ₹200,000 median for Water works in CHATRA (200% above, 156 peer works)
- 119 days beyond expected completion
Read more (1 more)Show less- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹6.00 L | MEDIUM 57 | |
| 12 | Repairing of Baherwa Ahar Water — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - 111 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹1.50 L | MEDIUM 56
duplication 20delay 15agency 15 | |
| 13 | Repairing of Dumaria Ahar Water — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - 115 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹2.00 L | MEDIUM 56
duplication 20delay 16agency 15 | |
| 14 | Construction of Atal Ashmiriti Bhawan in Pathalgada Community Buildings — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹500,000 against a ₹200,000 median for Community Buildings works in CHATRA (150% above, 96 peer works)
- 108 days beyond expected completion
Read more (1 more)Show less- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹5.00 L | MEDIUM 55 | |
| 15 | SITC for Blood Cell Counter Analyzer (CBC Machine & Bio Chem Health — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 585 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| CHATRA | ₹60.00 L | MEDIUM 54 | |
| 16 | SITC of infant baby warmer machine at various CHC/HSC/PSC/Ho Health — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 586 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| CHATRA | ₹60.00 L | MEDIUM 54 | |
| 17 | Repairing of Guhi Ahar Water — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - 119 days beyond expected completion
- 98% similarity with another nearby work
Read more (1 more)Show less- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹1.00 L | MEDIUM 53
delay 17agency 15duplication 15 | |
| 18 | Repair of Guhi Ahar Water — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - 119 days beyond expected completion
- 98% similarity with another nearby work
Read more (1 more)Show less- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹1.50 L | MEDIUM 52
delay 17agency 15duplication 15 | |
| 19 | Retrofitting of Chandravanshi Bhawan (Block-Kanhachatti, Pan Community Buildings — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in CHATRA (100% above, 96 peer works)
- 88 days beyond expected completion
Read more (1 more)Show less- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹4.00 L | MEDIUM 52 | |
| 20 | Construction of chabutra (Block-Kanhachatti, Panchayat-Kolha Community Buildings — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - 88 days beyond expected completion
- 98% similarity with another nearby work
Read more (1 more)Show less- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹1.00 L | MEDIUM 47
agency 15duplication 14delay 12 | |
| 21 | Construction of chabutra (Block-Kanhachatti, Panchayat-Kolha Community Buildings — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - 88 days beyond expected completion
- 98% similarity with another nearby work
Read more (1 more)Show less- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹1.00 L | MEDIUM 47
agency 15duplication 14delay 12 | |
| 22 | Construction of Chabutra near shiv mandir (Block-Kanhachatti Religious & Cultural — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - 88 days beyond expected completion
- 98% similarity with another nearby work
Read more (1 more)Show less- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹1.00 L | MEDIUM 46
agency 15duplication 13delay 12 | |
| 23 | Repair of Dhani Ahar Water — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹300,000 against a ₹200,000 median for Water works in CHATRA (50% above, 156 peer works)
- 124 days beyond expected completion
Read more (1 more)Show less- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹3.00 L | MEDIUM 45 | |
| 24 | Repair of Sundardaha Uprahi Ahar Water — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹300,000 against a ₹200,000 median for Water works in CHATRA (50% above, 156 peer works)
- 124 days beyond expected completion
Read more (1 more)Show less- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹3.00 L | MEDIUM 45 | |
| 25 | Repairing of Devi Mandap Ahar Religious & Cultural — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹150,000 against a ₹100,000 median for Religious & Cultural works in CHATRA (50% above, 57 peer works)
- 119 days beyond expected completion
Read more (1 more)Show less- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹1.50 L | MEDIUM 44 | |