Construction of community hall
Community Buildings
Karnataka / RAICHUR — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) · Sanganna Amarappa Karadi (KOPPAL)
Overall risk score
64/100
Blended from the five components below, each weighted as shown.
Risk components
Cost34
Delay100
Duplication100
Agency68
Compliance0
Sanctioned
₹3.50 L
Delay
659d
Cost deviation
-13%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- 659 days beyond expected completionPublished dates
- 100% similarity with another nearby workAI · Sentence-BERT embeddings (all-MiniLM-L6-v2)
- Implementing agency has a 68% delay rate across its projectsStated compliance rule
Decision trail
Nobody has recorded a decision on this work yet.
Reads as a near-duplicate of work #28960 (sentence-embedding similarity 1.00, measured by all-MiniLM-L6-v2 on meaning rather than shared words; two works can legitimately share a description, so this is a prompt to check, not a finding)