Formation and gravelling road from R Ramjan Field to Rukmaba
Roads & Paving
Telangana / ADILABAD — ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) · Soyam Bapu Rao (ADILABAD)
Formation and gravelling road from R Ramjan Field to Rukmabai field
Overall risk score
58/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency54
Compliance0
Sanctioned
₹7.00 L
Delay
714d
Cost deviation
134%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹700,000 against a ₹299,660 median for Roads & Paving works in ADILABAD (134% above, 163 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 714 days beyond expected completionPublished dates
- Implementing agency has a 54% delay rate across its projectsStated compliance rule
Decision trail
Nobody has recorded a decision on this work yet.