Construction of auditorium over the assembly yard at Sichey

Education

Sikkim / GANGTOK — Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) · Indra Hang Subba (SIKKIM)

Construction of auditorium over the assembly yard at Sichey Government Senior Secondary School

Overall risk score
26/100
Blended from the five components below, each weighted as shown.
LOW

Risk components

Cost100
Delay0
Duplication0
Agency6
Compliance0
Sanctioned
₹39.99 L
Delay
0d
Cost deviation
301%
Work status
Completed

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹3,999,349 against a ₹998,572 median for Education works in GANGTOK (301% above, 28 peer works)Peer comparison · sector labelled by Gemini Flash Lite

Decision trail

Nobody has recorded a decision on this work yet.