CONSTRUCTION OF BALMIKI CHAUPAL WITH ONE HALL, VARANDA & TOI

Drainage & Sanitation

Uttar Pradesh / BAGHPAT — BAGHPAT(DISTRICT MAGISTRATE BAGHPAT_IDA) · Satya Pal Singh (BAGHPAT)

CONSTRUCTION OF BALMIKI CHAUPAL WITH ONE HALL, VARANDA & TOILET-BATHROOM

Overall risk score
54/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost70
Delay100
Duplication0
Agency76
Compliance0
Sanctioned
₹17.96 L
Delay
724d
Cost deviation
—
Fewer than 8 comparable works in this district and sector
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of rangeAI · Isolation Forest (scikit-learn)
  • 724 days beyond expected completionPublished dates
  • 1 payment still in progress, oldest 574 daysStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.