97 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | BAGHPAT(DISTRICT MAGISTRATE BAGHPAT_IDA) 1 high risk | 97 | 25 | ₹9.45 Cr | 8 | 26.0 | TECHKRITI INFRATECH PVT LTD 47% of spend · 7 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Rajkumar Sangwan BAGHPAT | 73 | ₹5.76 Cr | 3 |
| Surendra Singh Nagar Sitting Rajya Sabha | 21 | ₹99.78 L | 2 |
| Jayant Chaudhary Sitting Rajya Sabha | 3 | ₹2.69 Cr | 3 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 55 | ₹4.27 Cr | 2 |
| Water | 19 | ₹86.91 L | 2 |
| Community Buildings | 8 | ₹2.11 Cr | 1 |
| Education | 5 | ₹1.60 Cr | 2 |
| Street Lighting | 5 | ₹27.84 L | 1 |
| Sports | 3 | ₹13.57 L | 0 |
| Religious & Cultural | 1 | ₹12.58 L | 0 |
| Drainage & Sanitation | 1 | ₹6.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| This amount is for the construction of a 200m eight-lane PU ₹8,416,000 against a ₹3,751,200 median for Education works in BAGHPAT (124% above, 8 peer works) | BAGHPAT(DISTRICT MAGISTRATE BAGHPAT_IDA) | Recommended | ₹84.16 L | 566 d | +124% | 81.3 | HIGH |
| Lighting of public spaces
nahar ke pul ke pass
Working Agenc Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BAGHPAT(DISTRICT MAGISTRATE BAGHPAT_IDA) | Recommended | ₹1.44 L | 758 d | -78% | 68.7 | MEDIUM |
| light- talab ke pass Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BAGHPAT(DISTRICT MAGISTRATE BAGHPAT_IDA) | Recommended | ₹1.44 L | 758 d | -69% | 68.7 | MEDIUM |
| Construction of a 200 plus 100m extended six-lane synthetic ₹13,242,000 against a ₹1,193,500 median for Community Buildings works in BAGHPAT (1010% above, 24 peer works) | BAGHPAT(DISTRICT MAGISTRATE BAGHPAT_IDA) | Recommended | ₹1.32 Cr | — | +1010% | 56.3 | MEDIUM |
| Construction of a basketball and multi-sports outdoor court ₹5,281,400 against a ₹3,751,200 median for Education works in BAGHPAT (41% above, 8 peer works) | BAGHPAT(DISTRICT MAGISTRATE BAGHPAT_IDA) | Completed | ₹52.81 L | — | +41% | 52.5 | MEDIUM |
| Construction of khandnja from budhu field to krsnpal field v 201 days beyond expected completion | BAGHPAT(DISTRICT MAGISTRATE BAGHPAT_IDA) | Recommended | ₹5.50 L | 201 d | -30% | 43.8 | MEDIUM |
| Construction of khandnja from mukul tubewell to galexy inter 201 days beyond expected completion | BAGHPAT(DISTRICT MAGISTRATE BAGHPAT_IDA) | Recommended | ₹4.00 L | 201 d | -15% | 43.5 | MEDIUM |
| Construction of interlocking tiles on the road near the main 209 days beyond expected completion | BAGHPAT(DISTRICT MAGISTRATE BAGHPAT_IDA) | Recommended | ₹5.00 L | 209 d | -36% | 43.4 | MEDIUM |
| Construction of kharanja from the khet of Mangeram to from t 139 days beyond expected completion | BAGHPAT(DISTRICT MAGISTRATE BAGHPAT_IDA) | Recommended | ₹8.77 L | 139 d | +11% | 39.3 | LOW |
| Construction work of Interlocking road from the house of yog 139 days beyond expected completion | BAGHPAT(DISTRICT MAGISTRATE BAGHPAT_IDA) | Recommended | ₹7.11 L | 139 d | -10% | 38.6 | LOW |
| Construction work of the interlocking road from the chaudhar 139 days beyond expected completion | BAGHPAT(DISTRICT MAGISTRATE BAGHPAT_IDA) | Recommended | ₹7.33 L | 139 d | -7% | 38.5 | LOW |
| Construction of kharanja from the khet of devendra prdhan to 139 days beyond expected completion | BAGHPAT(DISTRICT MAGISTRATE BAGHPAT_IDA) | Recommended | ₹6.21 L | 139 d | -21% | 37.7 | LOW |
| Construction of khandnja from bhudev tubewell to rameswar fi Completed work has no photographic documentation on record | BAGHPAT(DISTRICT MAGISTRATE BAGHPAT_IDA) | Completed | ₹8.67 L | — | +85% | 37.0 | LOW |
| Construction of kharanja from Mukuls tube bell to galexy int 142 days beyond expected completion | BAGHPAT(DISTRICT MAGISTRATE BAGHPAT_IDA) | Recommended | ₹3.86 L | 142 d | -90% | 36.8 | LOW |
| Construction of kharanja from the Rishipal khet to surendra 142 days beyond expected completion | BAGHPAT(DISTRICT MAGISTRATE BAGHPAT_IDA) | Recommended | ₹2.79 L | 142 d | -65% | 36.8 | LOW |