Construction of cement road at Daregaon Ta.Dist. Jalna

Roads & Paving

Maharashtra / JALNA — JALNA(DISTRICT COLLECTOR JALNA_IDA) · Raosaheb Dadarao Danve (JALNA)

Overall risk score
66/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost46
Delay100
Duplication80
Agency87
Compliance0
Sanctioned
₹7.00 L
Delay
660d
Cost deviation
-30%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of rangeAI · Isolation Forest (scikit-learn)
  • 660 days beyond expected completionPublished dates
  • 99% similarity with another nearby workAI · Sentence-BERT embeddings (all-MiniLM-L6-v2)
  • Implementing agency has a 87% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.

Reads as a near-duplicate of work #22654 (sentence-embedding similarity 0.99, measured by all-MiniLM-L6-v2 on meaning rather than shared words; two works can legitimately share a description, so this is a prompt to check, not a finding)