Construction of Road or Pathway near Krishna River at Kankan
Roads & Paving
Karnataka / BAGALKOTE — BAGALKOTE(DEPUTY COMMISSIONER BAGALKOT_IDA) · Gaddigoudar Parvatagouda Chandanagouda (BAGALKOT)
Construction of Road or Pathway near Krishna River at Kankanawadi village
Overall risk score
53/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency20
Compliance0
Sanctioned
₹10.00 L
Delay
218d
Cost deviation
100%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹1,000,000 against a ₹500,000 median for Roads & Paving works in BAGALKOTE (100% above, 10 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 218 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.