276 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | BAGALKOTE(DEPUTY COMMISSIONER BAGALKOT_IDA) 1 high risk | 276 | 105 | ₹14.29 Cr | 32 | 19.6 | Chairman Nirmithi Kendra Bagalkot 18% of spend · 104 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Gaddigoudar Parvatagouda Chandanagouda BAGALKOT | 214 | ₹11.29 Cr | 14 |
| Narayanasa K. Bhandage Sitting Rajya Sabha | 61 | ₹2.85 Cr | 18 |
| Priyanka Satish Jarkiholi CHIKKODI | 1 | ₹15.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 240 | ₹12.44 Cr | 21 |
| Education | 18 | ₹1.02 Cr | 8 |
| Water | 7 | ₹22.20 L | 2 |
| Roads & Paving | 5 | ₹27.93 L | 1 |
| Equipment & Vehicles | 2 | ₹2.00 L | 0 |
| Religious & Cultural | 1 | ₹5.00 L | 0 |
| Boundary & Protection | 1 | ₹5.00 L | 0 |
| Sports | 1 | ₹10.00 L | 0 |
| Drainage & Sanitation | 1 | ₹10.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Consruction of Community Hall. ₹1,000,000 against a ₹499,989 median for Community Buildings works in BAGALKOTE (100% above, 412 peer works) | BAGALKOTE(DEPUTY COMMISSIONER BAGALKOT_IDA) | Recommended | ₹10.00 L | 211 d | +100% | 73.1 | HIGH |
| Repair and renovation work of government school building. ₹1,500,000 against a ₹482,500 median for Education works in BAGALKOTE (211% above, 34 peer works) | BAGALKOTE(DEPUTY COMMISSIONER BAGALKOT_IDA) | Recommended | ₹15.00 L | 115 d | +211% | 64.0 | MEDIUM |
| Repair and renovation work of government school building. ₹1,400,000 against a ₹482,500 median for Education works in BAGALKOTE (190% above, 34 peer works) | BAGALKOTE(DEPUTY COMMISSIONER BAGALKOT_IDA) | Recommended | ₹14.00 L | 115 d | +190% | 64.0 | MEDIUM |
| Construction of Community Hall in HULYAL Village, Property N ₹1,000,000 against a ₹499,989 median for Community Buildings works in BAGALKOTE (100% above, 412 peer works) | BAGALKOTE(DEPUTY COMMISSIONER BAGALKOT_IDA) | Recommended | ₹10.00 L | 87 d | +100% | 60.1 | MEDIUM |
| Construction of Community Hall. 285 days beyond expected completion | BAGALKOTE(DEPUTY COMMISSIONER BAGALKOT_IDA) | Recommended | ₹4.00 L | 285 d | -20% | 56.3 | MEDIUM |
| Repair and renovation work of government school building. ₹800,000 against a ₹482,500 median for Education works in BAGALKOTE (66% above, 34 peer works) | BAGALKOTE(DEPUTY COMMISSIONER BAGALKOT_IDA) | Recommended | ₹8.00 L | 115 d | +66% | 55.5 | MEDIUM |
| Construction of Community Hall. 227 days beyond expected completion | BAGALKOTE(DEPUTY COMMISSIONER BAGALKOT_IDA) | Recommended | ₹3.00 L | 227 d | -40% | 55.1 | MEDIUM |
| Construction of Community Hall. 176 days beyond expected completion | BAGALKOTE(DEPUTY COMMISSIONER BAGALKOT_IDA) | Recommended | ₹5.00 L | 176 d | 0% | 53.8 | MEDIUM |
| Construction of Community Hall in SASALATTI Village Property 182 days beyond expected completion | BAGALKOTE(DEPUTY COMMISSIONER BAGALKOT_IDA) | Recommended | ₹5.00 L | 182 d | 0% | 53.6 | MEDIUM |
| Construction of Road or Pathway near Krishna River at Kankan ₹1,000,000 against a ₹500,000 median for Roads & Paving works in BAGALKOTE (100% above, 10 peer works) | BAGALKOTE(DEPUTY COMMISSIONER BAGALKOT_IDA) | Recommended | ₹10.00 L | 218 d | +100% | 53.1 | MEDIUM |
| Construction of Community Hall in JAMAKHANDI town Property N ₹1,000,000 against a ₹499,989 median for Community Buildings works in BAGALKOTE (100% above, 412 peer works) | BAGALKOTE(DEPUTY COMMISSIONER BAGALKOT_IDA) | Recommended | ₹10.00 L | 226 d | +100% | 53.1 | MEDIUM |
| Repair and renovation work of government school building. ₹715,000 against a ₹482,500 median for Education works in BAGALKOTE (48% above, 34 peer works) | BAGALKOTE(DEPUTY COMMISSIONER BAGALKOT_IDA) | Recommended | ₹7.15 L | 115 d | +48% | 51.1 | MEDIUM |
| Repair and renovation work of government school building. ₹700,000 against a ₹482,500 median for Education works in BAGALKOTE (45% above, 34 peer works) | BAGALKOTE(DEPUTY COMMISSIONER BAGALKOT_IDA) | Recommended | ₹7.00 L | 115 d | +45% | 50.3 | MEDIUM |
| Construction and installation of Drinking water plant. 153 days beyond expected completion | BAGALKOTE(DEPUTY COMMISSIONER BAGALKOT_IDA) | Recommended | ₹3.20 L | 153 d | 0% | 50.2 | MEDIUM |
| Construction of Community Hall in TERDAL town Property No.29 182 days beyond expected completion | BAGALKOTE(DEPUTY COMMISSIONER BAGALKOT_IDA) | Recommended | ₹5.00 L | 182 d | 0% | 50.2 | MEDIUM |