Construction of Community Centre, Ward No. 62S, South Zone,

Community Buildings

Delhi / SOUTH — SOUTH(COMMISSIONER SOUTH) · Meenakashi Lekhi (NEW DELHI)

Construction of Community Centre, Ward No. 62S, South Zone, Masjid Moth, New Delhi.

Overall risk score
52/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost100
Delay100
Duplication0
Agency11
Compliance0
Sanctioned
₹1.66 Cr
Delay
905d
Cost deviation
—
Fewer than 8 comparable works in this district and sector
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of rangeAI · Isolation Forest (scikit-learn)
  • 905 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.