Multi Purpose Play System
Sports
Delhi / EAST — EAST(COMMISSIONER EAST) · Manoj Tiwari (NORTH EAST DELHI)
Overall risk score
49/100
Blended from the five components below, each weighted as shown.
Risk components
Cost87
Delay100
Duplication0
Agency12
Compliance0
Sanctioned
₹7.99 L
Delay
544d
Cost deviation
87%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹799,000 against a ₹426,472 median for Sports works in EAST (87% above, 70 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 544 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.