construction of CC interlocking road from damar rode towoard

Roads & Paving

Uttar Pradesh / HARDOI — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) · Ashok Kumar Rawat (MISRIKH)

construction of CC interlocking road from damar rode towoards to shyamu pal (tentative 100m ) amount 500000,

Overall risk score
40/100
Blended from the five components below, each weighted as shown.
LOW

Risk components

Cost34
Delay100
Duplication0
Agency42
Compliance0
Sanctioned
₹5.00 L
Delay
544d
Cost deviation
-52%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 544 days beyond expected completionPublished dates
  • Implementing agency has a 42% delay rate across its projectsStated compliance rule

Decision trail