GULAOTHI ME NEW THANE KE PICHHE TALAB KE PASS SARVJANIK ISTH
Street Lighting
Uttar Pradesh / BULANDSHAHR — BULANDSHAHR(DISTRICT MAGISTRATE BULANDSHAHR_IDA) · Surendra Singh Nagar (Sitting Rajya Sabha)
GULAOTHI ME NEW THANE KE PICHHE TALAB KE PASS SARVJANIK ISTHAL PAR HIGH MAST LIGHT
Overall risk score
60/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay51
Duplication100
Agency16
Compliance0
Sanctioned
₹6.60 L
Delay
91d
Cost deviation
135%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹660,000 against a ₹281,044 median for Street Lighting works in BULANDSHAHR (135% above, 344 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 91 days beyond expected completionPublished dates
- 100% similarity with another nearby workAI · Sentence-BERT embeddings (all-MiniLM-L6-v2)
Decision trail
Nobody has recorded a decision on this work yet.
Reads as a near-duplicate of work #50040 (sentence-embedding similarity 1.00, measured by all-MiniLM-L6-v2 on meaning rather than shared words; two works can legitimately share a description, so this is a prompt to check, not a finding)