CC ROAD NIRMAN- ₹1,000,000 against a ₹520,000 median for Roads & Paving works in DURG (92% above, 109 peer works)
- 724 days beyond expected completion
| DURG | ₹10.00 L | MEDIUM 70 |
SAMUDAYIK BHAWAN NIRMAN- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 741 days beyond expected completion
| DURG | ₹8.00 L | MEDIUM 61 |
KAKSH NIRMAN- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 722 days beyond expected completion
| DURG | ₹8.00 L | MEDIUM 60 |
SAMUDAYIK BHAWAN NIRMAN- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 741 days beyond expected completion
| DURG | ₹6.50 L | MEDIUM 60 |
SAMUDAYIK BHAWAN NIRMAN- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 741 days beyond expected completion
| DURG | ₹6.00 L | MEDIUM 60 |
SAMUDAYIK BHAWAN NIRMAN- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 742 days beyond expected completion
| DURG | ₹6.00 L | MEDIUM 60 |
SHEDH NIRMAN- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 724 days beyond expected completion
| DURG | ₹6.00 L | MEDIUM 59 |
SARVJANIK BHAWAN NIRMAN- 620 days beyond expected completion
- 100% similarity with another nearby work
| BEMETARA | ₹5.00 L | MEDIUM 55 |
pustkalaay evam baithak vyvstha- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 742 days beyond expected completion
| DURG | ₹5.00 L | MEDIUM 51 |
CC ROAD NIRMAN- ₹999,500 against a ₹520,000 median for Roads & Paving works in DURG (92% above, 109 peer works)
- 100% similarity with another nearby work
| DURG | ₹10.00 L | MEDIUM 45 |