417 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | HOWRAH(DISTRICT MAGISTRATE HOWRAH_IDA) | 417 | 238 | ₹21.74 Cr | 2 | 8.0 | PRAYAS 11% of spend · 95 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Prasun Banerjee HOWRAH | 227 | ₹10.32 Cr | 0 |
| Sajda Ahmed ULUBERIA | 174 | ₹9.49 Cr | 2 |
| Kalyan Banerjee SREERAMPUR | 16 | ₹1.92 Cr | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 190 | ₹3.86 Cr | 0 |
| Roads & Paving | 100 | ₹7.29 Cr | 0 |
| Education | 38 | ₹2.95 Cr | 0 |
| Community Buildings | 28 | ₹2.24 Cr | 1 |
| Religious & Cultural | 20 | ₹71.90 L | 0 |
| Health | 10 | ₹1.28 Cr | 0 |
| Water | 9 | ₹34.56 L | 0 |
| Equipment & Vehicles | 8 | ₹1.45 Cr | 0 |
| Boundary & Protection | 8 | ₹60.33 L | 0 |
| Sports | 4 | ₹59.97 L | 1 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of office building of Grhbhwanipur Sonatala Gra ₹3,000,000 against a ₹598,376 median for Community Buildings works in HOWRAH (401% above, 45 peer works) | HOWRAH(DISTRICT MAGISTRATE HOWRAH_IDA) | Recommended | ₹30.00 L | 269 d | +401% | 50.4 | MEDIUM |
| Construction of Gym Building and installation of equipments Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | HOWRAH(DISTRICT MAGISTRATE HOWRAH_IDA) | Recommended | ₹35.00 L | 225 d | 0% | 43.1 | MEDIUM |
| Construction of Cold Chain room at Kamalpur Rural Hospital Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | HOWRAH(DISTRICT MAGISTRATE HOWRAH_IDA) | Recommended | ₹15.00 L | 361 d | +25% | 39.4 | LOW |
| CONSTRUCTION OF BURNNING PLACE WITH TUBE WELL AT NIBRA ANAND ₹967,730 against a ₹150,000 median for Water works in HOWRAH (545% above, 42 peer works) | HOWRAH(DISTRICT MAGISTRATE HOWRAH_IDA) | Recommended | ₹9.68 L | 96 d | +545% | 38.8 | LOW |
| Construction of Cement Concrete Road with cover drain and pr ₹1,123,580 against a ₹498,914 median for Roads & Paving works in HOWRAH (125% above, 166 peer works) | HOWRAH(DISTRICT MAGISTRATE HOWRAH_IDA) | Recommended | ₹11.24 L | 86 d | +125% | 37.4 | LOW |
| Purchase of 1 no. X-Ray machine DR with all accessories for Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | HOWRAH(DISTRICT MAGISTRATE HOWRAH_IDA) | Recommended | ₹16.75 L | 176 d | +29% | 37.3 | LOW |
| Construction of Seminar Hall at Menoka Smriti Vidyamandir 370 days beyond expected completion | HOWRAH(DISTRICT MAGISTRATE HOWRAH_IDA) | Recommended | ₹5.00 L | 370 d | -16% | 34.2 | LOW |
| Construction of Chulli & Waiting Shed at Harali Burning Ghat 280 days beyond expected completion | HOWRAH(DISTRICT MAGISTRATE HOWRAH_IDA) | Recommended | ₹5.00 L | 280 d | -16% | 33.3 | LOW |
| Installation of HighMast Light Near Najir Para Jama Masjid 246 days beyond expected completion | HOWRAH(DISTRICT MAGISTRATE HOWRAH_IDA) | Recommended | ₹1.60 L | 246 d | +7% | 33.3 | LOW |
| Installation of Solar Energy system in Bagnan High School 246 days beyond expected completion | HOWRAH(DISTRICT MAGISTRATE HOWRAH_IDA) | Recommended | ₹5.00 L | 246 d | -16% | 33.1 | LOW |
| Construction of Community Hall at Kaniapur Mouza in Chandrab 246 days beyond expected completion | HOWRAH(DISTRICT MAGISTRATE HOWRAH_IDA) | Recommended | ₹5.00 L | 246 d | -16% | 33.1 | LOW |
| Construction of Security Gate and Boundarywall of Shyampur S 220 days beyond expected completion | HOWRAH(DISTRICT MAGISTRATE HOWRAH_IDA) | Recommended | ₹1.75 L | 220 d | -65% | 32.7 | LOW |
| Construction of Crematorium at Sehagori Uttar para Dag NO 01 217 days beyond expected completion | HOWRAH(DISTRICT MAGISTRATE HOWRAH_IDA) | Recommended | ₹2.00 L | 217 d | -49% | 32.4 | LOW |
| Construction of new P.C.C road with toe wall from Sk Para Pr ₹2,800,000 against a ₹498,914 median for Roads & Paving works in HOWRAH (461% above, 166 peer works) | HOWRAH(DISTRICT MAGISTRATE HOWRAH_IDA) | Recommended | ₹28.00 L | 42 d | +461% | 31.3 | LOW |
| Installation of Streetlight from Thakurranichak Malikpara to Completed work has no photographic documentation on record | HOWRAH(DISTRICT MAGISTRATE HOWRAH_IDA) | Completed | ₹5.99 L | — | +300% | 29.9 | LOW |