Open this link on a larger screen to see the verification queue.
404 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | BHADOHI(DISTRICT MAGISTRATE BHADOHI_IDA) | 404 | 273 | ₹7.63 Cr | 34 | 15.2 | Gandhi Construction And Supplier 54% of spend · 9 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Vinod Kumar Bind BHADOHI | 400 | ₹6.60 Cr | 31 |
| Jaya Amitabh Bachchan Sitting Rajya Sabha | 3 | ₹1.01 Cr | 2 |
| Seema Dwivedi Sitting Rajya Sabha | 1 | ₹2.18 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Other | 221 | ₹2.49 Cr | 20 |
| Religious & Cultural | 68 | ₹78.49 L | 5 |
| Roads & Paving | 48 | ₹2.81 Cr | 3 |
| Education | 17 | ₹19.54 L | 1 |
| Street Lighting | 17 | ₹90.17 L | 2 |
| Community Buildings | 14 | ₹17.71 L | 3 |
| Water | 10 | ₹11.79 L | 0 |
| Health | 6 | ₹11.85 L | 0 |
| Sports | 3 | ₹3.26 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| VIDHI NARAYAN PANDEY GRAM JAGGARNATHPUR AURAYI BHADOHI SAMPA ₹218,000 against a ₹118,971 median for Street Lighting works in BHADOHI (83% above, 18 peer works) | BHADOHI(DISTRICT MAGISTRATE BHADOHI_IDA) | Recommended | ₹2.18 L | 121 d | +83% | 64.9 | MEDIUM |
| GOPIGANJ VARD 01 MANAV KALYAN SEVA SAMITI VRADDH ASHRAM PARI ₹275,997 against a ₹118,971 median for Community Buildings works in BHADOHI (132% above, 15 peer works) | BHADOHI(DISTRICT MAGISTRATE BHADOHI_IDA) | Recommended | ₹2.76 L | 165 d | +132% | 55.2 | MEDIUM |
| GOPIGANJ VARD NO 3 BADE SHIV MANDIR KE PARISAR ME ₹275,997 against a ₹118,971 median for Religious & Cultural works in BHADOHI (132% above, 69 peer works) | BHADOHI(DISTRICT MAGISTRATE BHADOHI_IDA) | Recommended | ₹2.76 L | 165 d | +132% | 55.2 | MEDIUM |
| GYANPUR VARD 06 JILA ASPTAL KE PARISAR ME ₹275,997 against a ₹107,898 median for Other works in BHADOHI (156% above, 221 peer works) | BHADOHI(DISTRICT MAGISTRATE BHADOHI_IDA) | Recommended | ₹2.76 L | 165 d | +156% | 55.2 | MEDIUM |
| construction of interlocking road in gram sabha sahesipur ne ₹4,666,386 against a ₹831,449 median for Roads & Paving works in BHADOHI (461% above, 80 peer works) | BHADOHI(DISTRICT MAGISTRATE BHADOHI_IDA) | Completed | ₹46.66 L | — | +461% | 52.3 | MEDIUM |
| construction of interlocking road in bhaidpur(hameedpatti) n ₹4,668,192 against a ₹831,449 median for Roads & Paving works in BHADOHI (461% above, 80 peer works) | BHADOHI(DISTRICT MAGISTRATE BHADOHI_IDA) | Completed | ₹46.68 L | — | +461% | 52.3 | MEDIUM |
| Gram Sabha Ajaypur me hanuman mandir ke pas sadak par 304 days beyond expected completion | BHADOHI(DISTRICT MAGISTRATE BHADOHI_IDA) | Recommended | ₹1.19 L | 304 d | -86% | 48.7 | MEDIUM |
| Gram Sabha Chhanaura Hanuman Mandir ke pas 304 days beyond expected completion | BHADOHI(DISTRICT MAGISTRATE BHADOHI_IDA) | Recommended | ₹1.19 L | 304 d | +0% | 46.3 | MEDIUM |
| Gram Sabha Bavai me Panchayat Bhavan ke pas 304 days beyond expected completion | BHADOHI(DISTRICT MAGISTRATE BHADOHI_IDA) | Recommended | ₹1.19 L | 304 d | +0% | 45.8 | MEDIUM |
| Gram Sabha Ahimanpur me Dinesh Mishra Ki dukaan Ke samne 320 days beyond expected completion | BHADOHI(DISTRICT MAGISTRATE BHADOHI_IDA) | Recommended | ₹1.19 L | 320 d | +10% | 41.6 | MEDIUM |
| Gram Sabha Parshurampur me Chaurahe par 304 days beyond expected completion | BHADOHI(DISTRICT MAGISTRATE BHADOHI_IDA) | Recommended | ₹1.19 L | 304 d | +10% | 41.3 | MEDIUM |
| Gram Sabha Jagapur Padan me Chaurahe par 304 days beyond expected completion | BHADOHI(DISTRICT MAGISTRATE BHADOHI_IDA) | Recommended | ₹1.19 L | 304 d | +10% | 41.3 | MEDIUM |
| Gram Sabha Vijayipur me Rang lal ke ghar ke pas 304 days beyond expected completion | BHADOHI(DISTRICT MAGISTRATE BHADOHI_IDA) | Recommended | ₹1.19 L | 304 d | +10% | 41.3 | MEDIUM |
| Gram Sabha Pakri Khurd me Ranmdhani bind ke ghar ke pas 304 days beyond expected completion | BHADOHI(DISTRICT MAGISTRATE BHADOHI_IDA) | Recommended | ₹1.19 L | 304 d | +10% | 41.3 | MEDIUM |
| Gram Sabha Akodha me Madan lal ke ghar ke pas trimuhani par 304 days beyond expected completion | BHADOHI(DISTRICT MAGISTRATE BHADOHI_IDA) | Recommended | ₹1.19 L | 304 d | +10% | 41.3 | MEDIUM |