248 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | KHAMMAM(DISTRICT COLLECTOR KHAMMAM_IDA) | 248 | 36 | ₹12.67 Cr | 13 | 14.7 | District Educational Officer Khammam 18% of spend · 29 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Ramasahayam Raghuram Reddy KHAMMAM | 167 | ₹5.56 Cr | 0 |
| Renuka Chowdhury Sitting Rajya Sabha | 42 | ₹2.32 Cr | 5 |
| Ravi Chandra Vaddiraju Sitting Rajya Sabha | 26 | ₹1.11 Cr | 7 |
| B. Parthasaradhi Reddy Sitting Rajya Sabha | 13 | ₹3.68 Cr | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 133 | ₹8.79 Cr | 8 |
| Water | 64 | ₹73.50 L | 1 |
| Drainage & Sanitation | 13 | ₹69.00 L | 1 |
| Education | 12 | ₹87.29 L | 3 |
| Street Lighting | 12 | ₹53.50 L | 0 |
| Health | 4 | ₹37.74 L | 0 |
| Community Buildings | 3 | ₹29.99 L | 0 |
| Boundary & Protection | 2 | ₹9.50 L | 0 |
| Sports | 2 | ₹13.00 L | 0 |
| Equipment & Vehicles | 2 | ₹9.95 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Laying of CC Road from Aithanaboina Veerababu (H) to Aithana 173 days beyond expected completion | KHAMMAM(DISTRICT COLLECTOR KHAMMAM_IDA) | Recommended | ₹1.40 L | 173 d | -72% | 53.4 | MEDIUM |
| Laying of CC Road from Regalla Nageshwar Rao (H) to Keesara 173 days beyond expected completion | KHAMMAM(DISTRICT COLLECTOR KHAMMAM_IDA) | Recommended | ₹1.40 L | 173 d | -72% | 53.4 | MEDIUM |
| Laying of CC Road from Danda Dhanamma (H) to Danda Venkatesh 173 days beyond expected completion | KHAMMAM(DISTRICT COLLECTOR KHAMMAM_IDA) | Recommended | ₹3.00 L | 173 d | -40% | 52.7 | MEDIUM |
| Laying of CC Road from Bommala Rambabu(H) to Avula Elamancha 157 days beyond expected completion | KHAMMAM(DISTRICT COLLECTOR KHAMMAM_IDA) | Recommended | ₹3.50 L | 157 d | -30% | 50.4 | MEDIUM |
| Drilling of Bore well and Fix Hand Pump nearby Bhaktha Anj ₹120,000 against a ₹80,000 median for Water works in KHAMMAM (50% above, 67 peer works) | KHAMMAM(DISTRICT COLLECTOR KHAMMAM_IDA) | Recommended | ₹1.20 L | 99 d | +50% | 48.7 | MEDIUM |
| Construction of Library Building at Ward No.06 in New Laxmip ₹1,500,000 against a ₹497,370 median for Education works in KHAMMAM (202% above, 26 peer works) | KHAMMAM(DISTRICT COLLECTOR KHAMMAM_IDA) | Recommended | ₹15.00 L | — | +202% | 47.5 | MEDIUM |
| Construction of Slab and Culvert at CHINTHAREVU AT KONIJERLA ₹2,000,000 against a ₹498,504 median for Roads & Paving works in KHAMMAM (301% above, 347 peer works) | KHAMMAM(DISTRICT COLLECTOR KHAMMAM_IDA) | Recommended | ₹20.00 L | — | +301% | 47.5 | MEDIUM |
| Construction of Side Drainage from Balapeta Bodrai to Balape ₹2,000,000 against a ₹400,000 median for Drainage & Sanitation works in KHAMMAM (400% above, 23 peer works) | KHAMMAM(DISTRICT COLLECTOR KHAMMAM_IDA) | Recommended | ₹20.00 L | — | +400% | 47.5 | MEDIUM |
| Construction of CC road on 50 feet road from Gollagudem roa ₹1,000,000 against a ₹498,504 median for Roads & Paving works in KHAMMAM (101% above, 347 peer works) | KHAMMAM(DISTRICT COLLECTOR KHAMMAM_IDA) | Recommended | ₹10.00 L | — | +101% | 47.5 | MEDIUM |
| Construction of Additional Class room for Computer Laborator ₹1,300,000 against a ₹497,370 median for Education works in KHAMMAM (161% above, 26 peer works) | KHAMMAM(DISTRICT COLLECTOR KHAMMAM_IDA) | Recommended | ₹13.00 L | — | +161% | 47.5 | MEDIUM |
| Laying of 1.2 Km Black Top Road in Gangaram Village as per t ₹29,495,741 against a ₹498,504 median for Roads & Paving works in KHAMMAM (5817% above, 347 peer works) | KHAMMAM(DISTRICT COLLECTOR KHAMMAM_IDA) | Recommended | ₹2.95 Cr | — | +5817% | 47.5 | MEDIUM |
| Construction of Culvert at Ward No.36, Gandhi Chowk, Khammam 114 days beyond expected completion | KHAMMAM(DISTRICT COLLECTOR KHAMMAM_IDA) | Recommended | ₹6.00 L | 114 d | +20% | 44.9 | MEDIUM |
| Construction of Compound wall at Mittapalli ZPHS High School ₹900,000 against a ₹497,370 median for Education works in KHAMMAM (81% above, 26 peer works) | KHAMMAM(DISTRICT COLLECTOR KHAMMAM_IDA) | Recommended | ₹9.00 L | — | +81% | 42.7 | MEDIUM |
| Drilling of Bore well and Fix Hand Pump nearby Kanakadurga Completed work has no photographic documentation on record | KHAMMAM(DISTRICT COLLECTOR KHAMMAM_IDA) | Completed | ₹1.20 L | — | +50% | 39.4 | LOW |
| Drilling of Bore well and Fix Hand Pump Nearby 24 hours Tap Completed work has no photographic documentation on record | KHAMMAM(DISTRICT COLLECTOR KHAMMAM_IDA) | Completed | ₹1.20 L | — | +50% | 39.4 | LOW |