191 works across 1 implementing agency, recommended by 5 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | JANGOAN(DISTRICT COLLECTOR JANGAON_IDA) | 191 | 100 | ₹5.19 Cr | 45 | 27.4 | Himalaya Bore Wells 32% of spend · 14 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Kadiyam Kavya WARANGEL | 94 | ₹3.51 Cr | 42 |
| Damodar Rao Divakonda Sitting Rajya Sabha | 45 | ₹54.78 L | 1 |
| Chamala Kiran Kumar Reddy BHONGIR | 44 | ₹63.89 L | 0 |
| Ravi Chandra Vaddiraju Sitting Rajya Sabha | 7 | ₹39.84 L | 2 |
| G Kishan Reddy SECUNDERABAD | 1 | ₹10.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 76 | ₹1.09 Cr | 22 |
| Water | 71 | ₹1.22 Cr | 19 |
| Community Buildings | 21 | ₹1.75 Cr | 4 |
| Roads & Paving | 8 | ₹44.92 L | 0 |
| Education | 5 | ₹23.60 L | 0 |
| Drainage & Sanitation | 4 | ₹24.85 L | 0 |
| Equipment & Vehicles | 2 | ₹3.36 L | 0 |
| Religious & Cultural | 1 | ₹59,911 | 0 |
| Other | 1 | ₹94,407 | 0 |
| Sports | 1 | ₹4.99 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Community Hall Near Sevalal Temple at Pedda 328 days beyond expected completion | JANGOAN(DISTRICT COLLECTOR JANGAON_IDA) | Recommended | ₹4.99 L | 328 d | -33% | 57.9 | MEDIUM |
| Construction of Community Hall Near SC Colony, Palakurthy (V 328 days beyond expected completion | JANGOAN(DISTRICT COLLECTOR JANGAON_IDA) | Recommended | ₹4.99 L | 328 d | -33% | 57.9 | MEDIUM |
| Construction of Community Hall at Manchuppula(V) of Palakur 323 days beyond expected completion | JANGOAN(DISTRICT COLLECTOR JANGAON_IDA) | Recommended | ₹5.00 L | 323 d | -33% | 57.8 | MEDIUM |
| (10) HIGH MAST LED LIGHTS FROM JEEDIKAL (BT) ROAD TO ALAMPAL ₹500,000 against a ₹200,000 median for Street Lighting works in JANGOAN (150% above, 118 peer works) | JANGOAN(DISTRICT COLLECTOR JANGAON_IDA) | Recommended | ₹5.00 L | 299 d | +150% | 54.4 | MEDIUM |
| PROVIDING DRINKING WATER PLANT TO TRIBALL RESIDENTIAL AND JU ₹300,000 against a ₹149,644 median for Water works in JANGOAN (100% above, 113 peer works) | JANGOAN(DISTRICT COLLECTOR JANGAON_IDA) | Recommended | ₹3.00 L | 172 d | +100% | 53.3 | MEDIUM |
| PROVIDING DRINKING WATER PLANT TO MLA CAMP OFFICE IN PALAKUR ₹300,000 against a ₹149,644 median for Water works in JANGOAN (100% above, 113 peer works) | JANGOAN(DISTRICT COLLECTOR JANGAON_IDA) | Recommended | ₹3.00 L | 172 d | +100% | 53.3 | MEDIUM |
| PROVIDING DRINIKING WATER PLANT TO RAMRAJPALLY VILLAGE OF DE ₹300,000 against a ₹149,644 median for Water works in JANGOAN (100% above, 113 peer works) | JANGOAN(DISTRICT COLLECTOR JANGAON_IDA) | Recommended | ₹3.00 L | 172 d | +100% | 53.3 | MEDIUM |
| PROVIDING PIPE LINE IN KODAKANDLA VILLAGE AND MANDAL ₹300,000 against a ₹149,644 median for Water works in JANGOAN (100% above, 113 peer works) | JANGOAN(DISTRICT COLLECTOR JANGAON_IDA) | Recommended | ₹3.00 L | 172 d | +100% | 53.3 | MEDIUM |
| CONSTRUCTION OF COMMUNITY HALL AT ZAFFERGADH VILLAGE AND MAN ₹1,500,000 against a ₹745,982 median for Community Buildings works in JANGOAN (101% above, 30 peer works) | JANGOAN(DISTRICT COLLECTOR JANGAON_IDA) | Recommended | ₹15.00 L | 172 d | +101% | 53.3 | MEDIUM |
| AUGUMENTATION OF PWC SCHEME ₹500,000 against a ₹149,644 median for Water works in JANGOAN (234% above, 113 peer works) | JANGOAN(DISTRICT COLLECTOR JANGAON_IDA) | Recommended | ₹5.00 L | — | +234% | 49.4 | MEDIUM |
| SUPPLY AND INSTALLATION OF 2000LPH RO PLANT ₹450,000 against a ₹149,644 median for Water works in JANGOAN (201% above, 113 peer works) | JANGOAN(DISTRICT COLLECTOR JANGAON_IDA) | Recommended | ₹4.50 L | 133 d | +201% | 47.9 | MEDIUM |
| Drilling of Bore Well and Erection of Pump Set at Fathepur V ₹250,000 against a ₹149,644 median for Water works in JANGOAN (67% above, 113 peer works) | JANGOAN(DISTRICT COLLECTOR JANGAON_IDA) | Recommended | ₹2.50 L | 234 d | +67% | 46.2 | MEDIUM |
| 1000 LPH RO Water Plant ₹300,000 against a ₹149,644 median for Water works in JANGOAN (100% above, 113 peer works) | JANGOAN(DISTRICT COLLECTOR JANGAON_IDA) | Recommended | ₹3.00 L | 108 d | +100% | 44.4 | MEDIUM |
| Providing Water Supply at Srirampally hamlet of Sreepathip ₹320,000 against a ₹149,644 median for Water works in JANGOAN (114% above, 113 peer works) | JANGOAN(DISTRICT COLLECTOR JANGAON_IDA) | Recommended | ₹3.20 L | 108 d | +114% | 44.4 | MEDIUM |
| Electrification Works- Installation of LED Street Lights 90 days beyond expected completion | JANGOAN(DISTRICT COLLECTOR JANGAON_IDA) | Recommended | ₹2.00 L | 90 d | 0% | 42.1 | MEDIUM |