103 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | KARUR(DISTRICT COLLECTOR KARUR_IDA) | 103 | 59 | ₹8.73 Cr | 4 | 14.0 | P S STALIN 17% of spend · 21 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| S Jothimani KARUR | 96 | ₹7.43 Cr | 4 |
| Arun Nehru PERAMBALUR | 6 | ₹1.14 Cr | 0 |
| K.R.N. Rajeshkumar Sitting Rajya Sabha | 1 | ₹15.17 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Education | 77 | ₹6.01 Cr | 4 |
| Community Buildings | 8 | ₹63.97 L | 0 |
| Health | 7 | ₹67.95 L | 0 |
| Water | 6 | ₹98.38 L | 0 |
| Equipment & Vehicles | 2 | ₹14.33 L | 0 |
| Drainage & Sanitation | 1 | ₹13.00 L | 0 |
| Religious & Cultural | 1 | ₹7.00 L | 0 |
| Roads & Paving | 1 | ₹7.50 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Classroom in Government Higher secondary Sch ₹2,100,000 against a ₹199,900 median for Education works in KARUR (951% above, 136 peer works) | KARUR(DISTRICT COLLECTOR KARUR_IDA) | Recommended | ₹21.00 L | 246 d | +951% | 52.0 | MEDIUM |
| Purchase of Smart Class for 5 Classrooms in Government Arts ₹993,825 against a ₹199,900 median for Education works in KARUR (397% above, 136 peer works) | KARUR(DISTRICT COLLECTOR KARUR_IDA) | Completed | ₹9.94 L | — | +397% | 47.0 | MEDIUM |
| Purchase of Smart Class for 5 Classrooms in Government Arts ₹993,825 against a ₹199,900 median for Education works in KARUR (397% above, 136 peer works) | KARUR(DISTRICT COLLECTOR KARUR_IDA) | Completed | ₹9.94 L | — | +397% | 47.0 | MEDIUM |
| Construction of Library Building, Skill Development and Empl ₹5,000,000 against a ₹199,900 median for Education works in KARUR (2401% above, 136 peer works) | KARUR(DISTRICT COLLECTOR KARUR_IDA) | Recommended | ₹50.00 L | 114 d | +2401% | 42.9 | MEDIUM |
| Purchase of 11 motorized tricycles for Differently Abled in ₹1,133,000 against a ₹96,011 median for Equipment & Vehicles works in KARUR (1080% above, 8 peer works) | KARUR(DISTRICT COLLECTOR KARUR_IDA) | Recommended | ₹11.33 L | 83 d | +1080% | 38.6 | LOW |
| Construction of Library and Skill Development Center ₹4,000,000 against a ₹199,900 median for Education works in KARUR (1901% above, 136 peer works) | KARUR(DISTRICT COLLECTOR KARUR_IDA) | Recommended | ₹40.00 L | — | +1901% | 38.5 | LOW |
| Construction of library building and skill development cente ₹5,000,000 against a ₹199,900 median for Education works in KARUR (2401% above, 136 peer works) | KARUR(DISTRICT COLLECTOR KARUR_IDA) | Recommended | ₹50.00 L | — | +2401% | 38.5 | LOW |
| Construction of Bus shed in Kannavai Bus stop,Kadavur Pancha Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | KARUR(DISTRICT COLLECTOR KARUR_IDA) | Recommended | ₹8.00 L | 279 d | +0% | 37.0 | LOW |
| Construction of OHT capacity of 60000 liters in the old war Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | KARUR(DISTRICT COLLECTOR KARUR_IDA) | Completed | ₹15.17 L | — | 0% | 32.7 | LOW |
| Construction of Bus shed opposite to VSB College, Karudaiyam Completed work has no photographic documentation on record | KARUR(DISTRICT COLLECTOR KARUR_IDA) | Completed | ₹8.00 L | — | +300% | 31.5 | LOW |
| Purchase of Washing Machine for the Government Medical Colle Completed work has no photographic documentation on record | KARUR(DISTRICT COLLECTOR KARUR_IDA) | Completed | ₹19.27 L | — | +864% | 31.5 | LOW |
| Construction of Additional Classroom in Panchayat Union Prim Completed work has no photographic documentation on record | KARUR(DISTRICT COLLECTOR KARUR_IDA) | Completed | ₹15.00 L | — | +650% | 31.5 | LOW |
| Construction of 30,000 Litres Over Head Tank (OHT) in Vaduga Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | KARUR(DISTRICT COLLECTOR KARUR_IDA) | Recommended | ₹16.60 L | 116 d | +9% | 29.2 | LOW |
| Construction of Bus shelter in Paaraiyur Bus stop, Sendamang 137 days beyond expected completion | KARUR(DISTRICT COLLECTOR KARUR_IDA) | Recommended | ₹8.00 L | 137 d | +0% | 29.2 | LOW |
| Antenatal Mother Screening and Follow-up Center at PHC ₹3,000,000 against a ₹700,000 median for Health works in KARUR (329% above, 11 peer works) | KARUR(DISTRICT COLLECTOR KARUR_IDA) | Recommended | ₹30.00 L | — | +329% | 27.0 | LOW |