204 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | CUDDALORE(DISTRICT COLLECTOR CUDDALORE_IDA) 1 high risk | 204 | 140 | ₹17.67 Cr | 19 | 16.4 | BALASUBRAMANIAN 9% of spend · 76 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| M K Vishnu Prasad CUDDALORE | 117 | ₹10.20 Cr | 5 |
| S. Kalyanasundaram Sitting Rajya Sabha | 39 | ₹2.86 Cr | 6 |
| Thirumaavalavan Tholkappiyan CHIDAMBARAM | 32 | ₹3.89 Cr | 1 |
| R. Girirajan Sitting Rajya Sabha | 16 | ₹71.97 L | 7 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 83 | ₹4.09 Cr | 7 |
| Roads & Paving | 40 | ₹4.27 Cr | 3 |
| Community Buildings | 37 | ₹5.09 Cr | 7 |
| Education | 20 | ₹1.49 Cr | 0 |
| Religious & Cultural | 8 | ₹66.17 L | 0 |
| Water | 5 | ₹70.90 L | 0 |
| Other | 4 | ₹50.84 L | 1 |
| Health | 3 | ₹49.63 L | 1 |
| Boundary & Protection | 2 | ₹20.50 L | 0 |
| Drainage & Sanitation | 2 | ₹14.96 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Marriage hall for Adi Dravidar Colony in Ora ₹5,000,000 against a ₹899,449 median for Community Buildings works in CUDDALORE (456% above, 52 peer works) | CUDDALORE(DISTRICT COLLECTOR CUDDALORE_IDA) | Recommended | ₹50.00 L | 352 d | +456% | 71.5 | HIGH |
| Construction of New Public Distribution shop building in war ₹1,800,000 against a ₹899,449 median for Community Buildings works in CUDDALORE (100% above, 52 peer works) | CUDDALORE(DISTRICT COLLECTOR CUDDALORE_IDA) | Recommended | ₹18.00 L | 300 d | +100% | 59.6 | MEDIUM |
| Construction of New Public Distribution shop building in war ₹1,800,000 against a ₹899,449 median for Community Buildings works in CUDDALORE (100% above, 52 peer works) | CUDDALORE(DISTRICT COLLECTOR CUDDALORE_IDA) | Recommended | ₹18.00 L | 300 d | +100% | 59.6 | MEDIUM |
| Providing Highmast light @ Near Sivan Koil Keezhkalpoondi P 624 days beyond expected completion | CUDDALORE(DISTRICT COLLECTOR CUDDALORE_IDA) | Recommended | ₹4.50 L | 624 d | +0% | 54.7 | MEDIUM |
| Providing Highmast light @ near Mariyamman Koil street, SC 624 days beyond expected completion | CUDDALORE(DISTRICT COLLECTOR CUDDALORE_IDA) | Recommended | ₹4.50 L | 624 d | +0% | 54.7 | MEDIUM |
| Providing Highmast light @ near Mariyamman Koil street, Back 624 days beyond expected completion | CUDDALORE(DISTRICT COLLECTOR CUDDALORE_IDA) | Recommended | ₹4.50 L | 624 d | +0% | 54.7 | MEDIUM |
| Providing Highmast light @ near Bus stand Sirupakkam Panchay 624 days beyond expected completion | CUDDALORE(DISTRICT COLLECTOR CUDDALORE_IDA) | Recommended | ₹4.50 L | 624 d | +0% | 54.7 | MEDIUM |
| Providing Highmast light @ near Mariyamman Koil street, SC 624 days beyond expected completion | CUDDALORE(DISTRICT COLLECTOR CUDDALORE_IDA) | Recommended | ₹4.50 L | 624 d | +0% | 54.7 | MEDIUM |
| Providing Highmast light (12M 150W 6 Light/Ladder Type) @ Ne 624 days beyond expected completion | CUDDALORE(DISTRICT COLLECTOR CUDDALORE_IDA) | Recommended | ₹4.50 L | 624 d | +0% | 54.7 | MEDIUM |
| Providing Highmast light (12M 150W 6 Light/Ladder Type) @ Pe 624 days beyond expected completion | CUDDALORE(DISTRICT COLLECTOR CUDDALORE_IDA) | Recommended | ₹4.50 L | 624 d | +0% | 54.7 | MEDIUM |
| Construction of a Public Distribution System Shop in Sevur P 197 days beyond expected completion | CUDDALORE(DISTRICT COLLECTOR CUDDALORE_IDA) | Recommended | ₹3.00 L | 197 d | -67% | 53.0 | MEDIUM |
| Construction of a Public Distribution System Shop in Tholar 197 days beyond expected completion | CUDDALORE(DISTRICT COLLECTOR CUDDALORE_IDA) | Recommended | ₹3.00 L | 197 d | -67% | 53.0 | MEDIUM |
| Construction of cement road on Krishnakuppam RC Colony Stree ₹1,999,644 against a ₹999,534 median for Roads & Paving works in CUDDALORE (100% above, 83 peer works) | CUDDALORE(DISTRICT COLLECTOR CUDDALORE_IDA) | Completed | ₹20.00 L | — | +100% | 46.5 | MEDIUM |
| Construction of cement road in the middle street of Kattiyan ₹1,999,791 against a ₹999,534 median for Roads & Paving works in CUDDALORE (100% above, 83 peer works) | CUDDALORE(DISTRICT COLLECTOR CUDDALORE_IDA) | Completed | ₹20.00 L | — | +100% | 46.5 | MEDIUM |
| CC Road to SKS Nagar Old Tasildar Office road (Ward 17) in K ₹2,000,000 against a ₹999,534 median for Roads & Paving works in CUDDALORE (100% above, 83 peer works) | CUDDALORE(DISTRICT COLLECTOR CUDDALORE_IDA) | Completed | ₹20.00 L | — | +100% | 46.5 | MEDIUM |