9 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Namchi(IMPLEMENTING DISTRICT AGENCY, NAMCHI) | 9 | 0 | ₹1.60 Cr | 6 | 42.5 | ASSISTANT ENGINEER SOUTH DISTRICT ZILLA PANCHAYAT 27% of spend · 6 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Dorjee Tshering Lepcha Sitting Rajya Sabha | 6 | ₹95.00 L | 3 |
| Indra Hang Subba SIKKIM | 3 | ₹65.00 L | 3 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Education | 4 | ₹70.00 L | 3 |
| Community Buildings | 2 | ₹50.00 L | 2 |
| Street Lighting | 2 | ₹25.00 L | 0 |
| Water | 1 | ₹15.00 L | 1 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of rooms and halls in Kaijaley Jr High School, 126 days beyond expected completion | Namchi(IMPLEMENTING DISTRICT AGENCY, NAMCHI) | Recommended | ₹10.00 L | 126 d | 0% | 52.7 | MEDIUM |
| Construction of drainage system near Government Sokey Junior Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Namchi(IMPLEMENTING DISTRICT AGENCY, NAMCHI) | Recommended | ₹40.00 L | 737 d | 0% | 52.0 | MEDIUM |
| Development of Play Ground at Upper Borong Primary School, S 118 days beyond expected completion | Namchi(IMPLEMENTING DISTRICT AGENCY, NAMCHI) | Recommended | ₹10.00 L | 118 d | 0% | 51.3 | MEDIUM |
| Site development and needed repair and renovation of Village Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Namchi(IMPLEMENTING DISTRICT AGENCY, NAMCHI) | Recommended | ₹10.00 L | 735 d | 0% | 46.6 | MEDIUM |
| Railing work in needed location at Assangthang Government Se Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Namchi(IMPLEMENTING DISTRICT AGENCY, NAMCHI) | Recommended | ₹15.00 L | 582 d | 0% | 46.5 | MEDIUM |
| Construction of common sitting area near Tek Gumpa Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Namchi(IMPLEMENTING DISTRICT AGENCY, NAMCHI) | Recommended | ₹40.00 L | — | 0% | 42.2 | MEDIUM |
| Lighting of Public Spaces Namthang Road at Mamring 100% similarity with another nearby work | Namchi(IMPLEMENTING DISTRICT AGENCY, NAMCHI) | Recommended | ₹15.00 L | — | 0% | 32.5 | LOW |
| Construction of School Ground of Banday Primary School Yanga 100% similarity with another nearby work | Namchi(IMPLEMENTING DISTRICT AGENCY, NAMCHI) | Recommended | ₹10.00 L | — | 0% | 29.2 | LOW |
| Lightining Of Public Spaces Near Tek Gumpa 100% similarity with another nearby work | Namchi(IMPLEMENTING DISTRICT AGENCY, NAMCHI) | Recommended | ₹10.00 L | — | 0% | 29.2 | LOW |