67 works across 1 implementing agency, recommended by 5 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Phalodi(DISTRICT COLLECTOR PHALODI_IDA) | 67 | 42 | ₹4.13 Cr | 7 | 21.8 | gram panchayat bhajanagar 7% of spend · 86 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Gajendra Singh Shekhawat JODHPUR | 54 | ₹2.85 Cr | 1 |
| Sonia Gandhi Sitting Rajya Sabha | 9 | ₹89.98 L | 5 |
| Madan Rathore Sitting Rajya Sabha | 2 | ₹12.50 L | 0 |
| Pramod Tiwari Sitting Rajya Sabha | 1 | ₹15.00 L | 1 |
| Randeep Singh Surjewala Sitting Rajya Sabha | 1 | ₹10.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Education | 46 | ₹2.42 Cr | 3 |
| Roads & Paving | 8 | ₹77.86 L | 3 |
| Boundary & Protection | 7 | ₹43.44 L | 0 |
| Community Buildings | 3 | ₹24.43 L | 1 |
| Religious & Cultural | 2 | ₹20.00 L | 0 |
| Water | 1 | ₹5.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Gravel Road from Baru Daamar Road upto Kohri 215 days beyond expected completion | Phalodi(DISTRICT COLLECTOR PHALODI_IDA) | Recommended | ₹10.00 L | 215 d | 0% | 58.2 | MEDIUM |
| MPLADS - 372
Construction work of public library in populate ₹1,000,000 against a ₹500,000 median for Education works in PHALODI (100% above, 63 peer works) | Phalodi(DISTRICT COLLECTOR PHALODI_IDA) | Recommended | ₹10.00 L | 573 d | +100% | 53.2 | MEDIUM |
| Construction of an Interlocking Road near the Rajasv Village 145 days beyond expected completion | Phalodi(DISTRICT COLLECTOR PHALODI_IDA) | Recommended | ₹10.00 L | 145 d | 0% | 51.9 | MEDIUM |
| Construction of an Interlocking Road near the Village Noore 145 days beyond expected completion | Phalodi(DISTRICT COLLECTOR PHALODI_IDA) | Recommended | ₹10.00 L | 145 d | 0% | 51.9 | MEDIUM |
| Construction of Public Library at Gram Panchayat - Bengti Ka ₹1,000,000 against a ₹500,000 median for Education works in PHALODI (100% above, 63 peer works) | Phalodi(DISTRICT COLLECTOR PHALODI_IDA) | Recommended | ₹10.00 L | — | +100% | 48.2 | MEDIUM |
| Construction of a public library in the Gram Panchayat premi ₹1,000,000 against a ₹500,000 median for Education works in PHALODI (100% above, 63 peer works) | Phalodi(DISTRICT COLLECTOR PHALODI_IDA) | Recommended | ₹10.00 L | — | +100% | 48.2 | MEDIUM |
| For construction of public community hall in Waas of Nurkhan ₹1,500,000 against a ₹600,000 median for Community Buildings works in PHALODI (150% above, 10 peer works) | Phalodi(DISTRICT COLLECTOR PHALODI_IDA) | Recommended | ₹15.00 L | — | +150% | 48.2 | MEDIUM |
| MPLADS - 152
Construction work of class room in Government H Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Phalodi(DISTRICT COLLECTOR PHALODI_IDA) | Recommended | ₹5.00 L | 733 d | 0% | 39.5 | LOW |
| MPLADS - 348
Construction work of boundary walls of crematio Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Phalodi(DISTRICT COLLECTOR PHALODI_IDA) | Recommended | ₹7.50 L | 586 d | 0% | 39.1 | LOW |
| MPLADS - 249
Construction work of Kharanja in Government Hig Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Phalodi(DISTRICT COLLECTOR PHALODI_IDA) | Recommended | ₹5.00 L | 717 d | 0% | 38.5 | LOW |
| MPLADS - 186
Work of construction of public community hall a Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Phalodi(DISTRICT COLLECTOR PHALODI_IDA) | Recommended | ₹5.00 L | 716 d | -17% | 38.5 | LOW |
| MPLADS - 292
Construction work of classroom in Government Hi 596 days beyond expected completion | Phalodi(DISTRICT COLLECTOR PHALODI_IDA) | Recommended | ₹6.00 L | 596 d | +20% | 37.7 | LOW |
| MPLADS - 265
Work of prayer place and tin shed in Government 597 days beyond expected completion | Phalodi(DISTRICT COLLECTOR PHALODI_IDA) | Recommended | ₹6.00 L | 597 d | +20% | 37.6 | LOW |
| MPLADS - 268
Construction work of classroom in Government Hi 597 days beyond expected completion | Phalodi(DISTRICT COLLECTOR PHALODI_IDA) | Recommended | ₹6.00 L | 597 d | +20% | 37.6 | LOW |
| MPLADS - 364
Construction work of boundary walls of Governme 573 days beyond expected completion | Phalodi(DISTRICT COLLECTOR PHALODI_IDA) | Recommended | ₹5.00 L | 573 d | 0% | 36.3 | LOW |