87 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | PALI(DISTRICT COLLECTOR PALI_IDA) 1 high risk | 87 | 18 | ₹6.33 Cr | 33 | 34.1 | NARPAT RAM 9% of spend · 233 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Madan Rathore Sitting Rajya Sabha | 47 | ₹3.31 Cr | 28 |
| P P Chaudhary PALI | 39 | ₹2.87 Cr | 4 |
| Ghanshyam Tiwari Sitting Rajya Sabha | 1 | ₹15.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 58 | ₹3.61 Cr | 22 |
| Roads & Paving | 9 | ₹92.88 L | 5 |
| Education | 8 | ₹67.50 L | 4 |
| Sports | 3 | ₹18.00 L | 1 |
| Religious & Cultural | 3 | ₹47.56 L | 1 |
| Drainage & Sanitation | 2 | ₹20.00 L | 0 |
| Street Lighting | 2 | ₹13.00 L | 0 |
| Equipment & Vehicles | 1 | ₹6.50 L | 0 |
| Boundary & Protection | 1 | ₹6.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction Work of Cement Concete Road From Panch Mokha Pu ₹1,600,000 against a ₹676,136 median for Roads & Paving works in PALI (137% above, 28 peer works) | PALI(DISTRICT COLLECTOR PALI_IDA) | Recommended | ₹16.00 L | 177 d | +137% | 74.3 | HIGH |
| Public Bus Stand Construction Work at Village Korta 217 days beyond expected completion | PALI(DISTRICT COLLECTOR PALI_IDA) | Recommended | ₹5.00 L | 217 d | 0% | 56.9 | MEDIUM |
| Public Bus Stand Construction Work at Village Bamnera 217 days beyond expected completion | PALI(DISTRICT COLLECTOR PALI_IDA) | Recommended | ₹5.00 L | 217 d | 0% | 56.9 | MEDIUM |
| Public Bus Stand Construction Work at Village Nowi 217 days beyond expected completion | PALI(DISTRICT COLLECTOR PALI_IDA) | Recommended | ₹5.00 L | 217 d | 0% | 56.9 | MEDIUM |
| Public Bus Stand Construction Work at Village Bharoonda 217 days beyond expected completion | PALI(DISTRICT COLLECTOR PALI_IDA) | Recommended | ₹5.00 L | 217 d | 0% | 56.9 | MEDIUM |
| Public Bus Stand Construction Work at Village Khiwandi 217 days beyond expected completion | PALI(DISTRICT COLLECTOR PALI_IDA) | Recommended | ₹5.00 L | 217 d | 0% | 56.9 | MEDIUM |
| Public Bus Stand Construction Work at Village Balupura 217 days beyond expected completion | PALI(DISTRICT COLLECTOR PALI_IDA) | Recommended | ₹5.00 L | 217 d | 0% | 56.9 | MEDIUM |
| Public Bus Stand Construction Work at Village Balana 217 days beyond expected completion | PALI(DISTRICT COLLECTOR PALI_IDA) | Recommended | ₹5.00 L | 217 d | 0% | 56.9 | MEDIUM |
| Public Bus Stand Construction Work at Village Netra 217 days beyond expected completion | PALI(DISTRICT COLLECTOR PALI_IDA) | Recommended | ₹5.00 L | 217 d | 0% | 56.9 | MEDIUM |
| Public Bus Stand Construction Work at Village Anoppura 217 days beyond expected completion | PALI(DISTRICT COLLECTOR PALI_IDA) | Recommended | ₹5.00 L | 217 d | 0% | 56.9 | MEDIUM |
| Public Bus Stand Construction Work at Village Lapod 217 days beyond expected completion | PALI(DISTRICT COLLECTOR PALI_IDA) | Recommended | ₹5.00 L | 217 d | 0% | 56.9 | MEDIUM |
| Public Bus Stand Construction Work at Village Dhana 217 days beyond expected completion | PALI(DISTRICT COLLECTOR PALI_IDA) | Recommended | ₹5.00 L | 217 d | 0% | 56.9 | MEDIUM |
| Public Bus Stand Construction Work at Village Birami 217 days beyond expected completion | PALI(DISTRICT COLLECTOR PALI_IDA) | Recommended | ₹5.00 L | 217 d | 0% | 56.9 | MEDIUM |
| Public Bus Stand Construction Work at Village Deotara 217 days beyond expected completion | PALI(DISTRICT COLLECTOR PALI_IDA) | Recommended | ₹5.00 L | 217 d | 0% | 56.9 | MEDIUM |
| Public Bus Stand Construction Work at Village Sindroo 217 days beyond expected completion | PALI(DISTRICT COLLECTOR PALI_IDA) | Recommended | ₹5.00 L | 217 d | 0% | 56.9 | MEDIUM |