13 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Jodhpur Gramin(DISTRICT COLLECTOR JODHPUR RURAL_IDA) | 13 | 8 | ₹94.95 L | 5 | 37.4 | SURYA CONSTRUCTION COMPANY 25% of spend · 6 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Madan Rathore Sitting Rajya Sabha | 5 | ₹29.99 L | 2 |
| Pramod Tiwari Sitting Rajya Sabha | 4 | ₹24.96 L | 0 |
| Sonia Gandhi Sitting Rajya Sabha | 3 | ₹29.99 L | 2 |
| P P Chaudhary PALI | 1 | ₹10.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 5 | ₹44.95 L | 2 |
| Religious & Cultural | 3 | ₹18.00 L | 1 |
| Community Buildings | 2 | ₹15.00 L | 2 |
| Street Lighting | 2 | ₹10.00 L | 0 |
| Education | 1 | ₹7.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| construction work of Resting place at public crematorium in 287 days beyond expected completion | Jodhpur Gramin(DISTRICT COLLECTOR JODHPUR RURAL_IDA) | Recommended | ₹6.00 L | 287 d | 0% | 59.0 | MEDIUM |
| Construction of Gravel Road from Gram Bewra to Lunawas Charn 112 days beyond expected completion | Jodhpur Gramin(DISTRICT COLLECTOR JODHPUR RURAL_IDA) | Recommended | ₹10.00 L | 112 d | +0% | 48.8 | MEDIUM |
| Strengthening of Gravel Road from Abadi Kshetra Fitkasani to 112 days beyond expected completion | Jodhpur Gramin(DISTRICT COLLECTOR JODHPUR RURAL_IDA) | Recommended | ₹10.00 L | 112 d | +0% | 48.8 | MEDIUM |
| SARVJANIK SABHA BHAWAN NIRMAN KARYA, KALPVRAKSH CHOWK,BILARA ₹1,000,000 against a ₹499,927 median for Community Buildings works in JODHPUR GRAMIN (100% above, 13 peer works) | Jodhpur Gramin(DISTRICT COLLECTOR JODHPUR RURAL_IDA) | Recommended | ₹10.00 L | 110 d | +100% | 45.2 | MEDIUM |
| Public Bus Stand Construction Work Village Mindoli 100% similarity with another nearby work | Jodhpur Gramin(DISTRICT COLLECTOR JODHPUR RURAL_IDA) | Recommended | ₹5.00 L | 70 d | +0% | 40.2 | MEDIUM |
| Computer room construction work in Government Higher Primary Completed work has no photographic documentation on record | Jodhpur Gramin(DISTRICT COLLECTOR JODHPUR RURAL_IDA) | Completed | ₹7.00 L | — | +40% | 39.4 | LOW |
| Construction of Gravel Road from Main Road to Ajit Nagar Sar Completed work has no photographic documentation on record | Jodhpur Gramin(DISTRICT COLLECTOR JODHPUR RURAL_IDA) | Completed | ₹9.99 L | — | +0% | 34.3 | LOW |
| For the construction work of gravel road from Naganarai temp Completed work has no photographic documentation on record | Jodhpur Gramin(DISTRICT COLLECTOR JODHPUR RURAL_IDA) | Completed | ₹9.97 L | — | 0% | 34.3 | LOW |
| construction work of Resting place at public crematorium in 100% similarity with another nearby work | Jodhpur Gramin(DISTRICT COLLECTOR JODHPUR RURAL_IDA) | Completed | ₹6.00 L | — | 0% | 29.5 | LOW |
| construction work of Resting place at public crematorium in 100% similarity with another nearby work | Jodhpur Gramin(DISTRICT COLLECTOR JODHPUR RURAL_IDA) | Completed | ₹6.00 L | — | 0% | 29.5 | LOW |
| For the construction work of gravel road from Prabhuram Megh 100% similarity with another nearby work | Jodhpur Gramin(DISTRICT COLLECTOR JODHPUR RURAL_IDA) | Completed | ₹4.99 L | — | -50% | 25.9 | LOW |
| Road lighting work from Teja Circle to Tejaram Jakhar Bagara 100% similarity with another nearby work | Jodhpur Gramin(DISTRICT COLLECTOR JODHPUR RURAL_IDA) | Completed | ₹5.00 L | — | 0% | 25.9 | LOW |
| Road lighting work from Gram Panchayat Bhundana Bhawan to Su 100% similarity with another nearby work | Jodhpur Gramin(DISTRICT COLLECTOR JODHPUR RURAL_IDA) | Completed | ₹5.00 L | — | 0% | 25.9 | LOW |