46 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | JALORE(DISTRICT COLLECTOR JALORE_IDA) 1 high risk | 46 | 21 | ₹3.15 Cr | 11 | 29.9 | Soni Medicals 10% of spend · 202 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Devji Mansingram Patel JALORE | 37 | ₹2.28 Cr | 5 |
| Mukul Wasnik Sitting Rajya Sabha | 5 | ₹47.44 L | 2 |
| Sonia Gandhi Sitting Rajya Sabha | 3 | ₹30.00 L | 3 |
| Pramod Tiwari Sitting Rajya Sabha | 1 | ₹10.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 32 | ₹2.08 Cr | 7 |
| Education | 6 | ₹39.69 L | 2 |
| Sports | 2 | ₹10.00 L | 0 |
| Equipment & Vehicles | 2 | ₹34.64 L | 1 |
| Street Lighting | 1 | ₹3.77 L | 0 |
| Community Buildings | 1 | ₹10.00 L | 1 |
| Religious & Cultural | 1 | ₹5.00 L | 0 |
| Boundary & Protection | 1 | ₹4.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Damrikaran WBM Sadak Jalberi Sadak to Gaushala, Gram Panchay ₹1,530,000 against a ₹598,305 median for Roads & Paving works in JALORE (156% above, 79 peer works) | JALORE(DISTRICT COLLECTOR JALORE_IDA) | Recommended | ₹15.30 L | 752 d | +156% | 75.5 | HIGH |
| interlocking road construction Norwa ₹998,902 against a ₹598,305 median for Roads & Paving works in JALORE (67% above, 79 peer works) | JALORE(DISTRICT COLLECTOR JALORE_IDA) | Recommended | ₹9.99 L | 558 d | +67% | 47.2 | MEDIUM |
| Purchase of medical equipments Leproscopy and Historoscopy Completed work has no photographic documentation on record | JALORE(DISTRICT COLLECTOR JALORE_IDA) | Completed | ₹24.64 L | — | 0% | 46.5 | MEDIUM |
| Construction of community hall with boundary walls of gram s Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JALORE(DISTRICT COLLECTOR JALORE_IDA) | Recommended | ₹10.00 L | 553 d | 0% | 43.1 | MEDIUM |
| Construction of CC Road at Aam Chohra, Mukhya Aabadi, Nimbau ₹1,000,000 against a ₹598,305 median for Roads & Paving works in JALORE (67% above, 79 peer works) | JALORE(DISTRICT COLLECTOR JALORE_IDA) | Recommended | ₹10.00 L | — | +67% | 42.3 | MEDIUM |
| Construction of CC Road from CC Road towards Shamshan Ghat, ₹1,000,000 against a ₹598,305 median for Roads & Paving works in JALORE (67% above, 79 peer works) | JALORE(DISTRICT COLLECTOR JALORE_IDA) | Recommended | ₹10.00 L | — | +67% | 42.3 | MEDIUM |
| Construction of CC Road from Nimbau towards Jodhavaas Vajesi ₹1,000,000 against a ₹598,305 median for Roads & Paving works in JALORE (67% above, 79 peer works) | JALORE(DISTRICT COLLECTOR JALORE_IDA) | Recommended | ₹10.00 L | — | +67% | 42.3 | MEDIUM |
| For the construction of CC road from main AAbadi Rani Bhatiy ₹999,960 against a ₹598,305 median for Roads & Paving works in JALORE (67% above, 79 peer works) | JALORE(DISTRICT COLLECTOR JALORE_IDA) | Completed | ₹10.00 L | — | +67% | 42.3 | MEDIUM |
| Construction of public library and reading room in Govt Sin ₹799,729 against a ₹549,856 median for Education works in JALORE (45% above, 24 peer works) | JALORE(DISTRICT COLLECTOR JALORE_IDA) | Recommended | ₹8.00 L | 553 d | +45% | 41.9 | MEDIUM |
| Construction of interlocking road from main road towards spo Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JALORE(DISTRICT COLLECTOR JALORE_IDA) | Recommended | ₹7.00 L | 553 d | +17% | 41.3 | MEDIUM |
| Construction of room Govt Primary School Kishangarh (Chhoond 556 days beyond expected completion | JALORE(DISTRICT COLLECTOR JALORE_IDA) | Recommended | ₹6.00 L | 556 d | +9% | 40.4 | MEDIUM |
| Extension (Increasing height of boundary wall) at the office 100% similarity with another nearby work | JALORE(DISTRICT COLLECTOR JALORE_IDA) | Recommended | ₹4.00 L | 62 d | 0% | 39.6 | LOW |
| Construction of CC Road from Main Road to Rajiv Gandhi Bhawa 100% similarity with another nearby work | JALORE(DISTRICT COLLECTOR JALORE_IDA) | Recommended | ₹1.50 L | 62 d | -75% | 39.6 | LOW |
| Construction of room at govt girl's primary school Khetlawas 551 days beyond expected completion | JALORE(DISTRICT COLLECTOR JALORE_IDA) | Recommended | ₹5.00 L | 551 d | -9% | 38.7 | LOW |
| Construction of road at lalaram lohar house to babulal puroh 551 days beyond expected completion | JALORE(DISTRICT COLLECTOR JALORE_IDA) | Recommended | ₹5.00 L | 551 d | -16% | 38.7 | LOW |