110 works across 1 implementing agency, recommended by 9 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) | 110 | 44 | ₹10.75 Cr | 35 | 35.4 | HUKAM SINGH CONSTRUCTION COMPANY 13% of spend · 39 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Sonia Gandhi Sitting Rajya Sabha | 42 | ₹4.79 Cr | 17 |
| Pramod Tiwari Sitting Rajya Sabha | 22 | ₹2.65 Cr | 6 |
| Ummeda Ram Beniwal BARMER | 16 | ₹65.22 L | 0 |
| Mukul Wasnik Sitting Rajya Sabha | 10 | ₹98.00 L | 4 |
| Madan Rathore Sitting Rajya Sabha | 8 | ₹44.50 L | 5 |
| Randeep Singh Surjewala Sitting Rajya Sabha | 4 | ₹45.79 L | 1 |
| Chunnilal Garasiya Sitting Rajya Sabha | 4 | ₹39.71 L | 1 |
| Arjun Ram Meghwal BIKANER | 2 | ₹29.92 L | 1 |
| Gajendra Singh Shekhawat JODHPUR | 2 | ₹8.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Education | 31 | ₹2.27 Cr | 13 |
| Community Buildings | 30 | ₹3.03 Cr | 10 |
| Roads & Paving | 30 | ₹3.84 Cr | 10 |
| Drainage & Sanitation | 5 | ₹45.00 L | 0 |
| Other | 4 | ₹39.77 L | 0 |
| Religious & Cultural | 3 | ₹30.00 L | 2 |
| Water | 3 | ₹24.50 L | 0 |
| Equipment & Vehicles | 2 | ₹3.50 L | 0 |
| Health | 1 | ₹9.00 L | 0 |
| Boundary & Protection | 1 | ₹10.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction Of Public Reading Rooms, Bathrooms/Urinals & in ₹1,500,000 against a ₹1,000,000 median for Roads & Paving works in JAISALMER (50% above, 67 peer works) | JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) | Recommended | ₹15.00 L | 432 d | +50% | 63.8 | MEDIUM |
| Revised: Construction work of public reading room in village ₹1,500,000 against a ₹984,268 median for Community Buildings works in JAISALMER (52% above, 98 peer works) | JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) | Recommended | ₹15.00 L | 397 d | +52% | 63.5 | MEDIUM |
| public reading room construction work
(Mehran's Dhani) ₹1,500,000 against a ₹984,268 median for Community Buildings works in JAISALMER (52% above, 98 peer works) | JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) | Recommended | ₹15.00 L | 338 d | +52% | 63.2 | MEDIUM |
| Sarwjanik Meghwal Samaj Hostal mein Hall Nirman Karya ; Work ₹1,495,786 against a ₹984,268 median for Community Buildings works in JAISALMER (52% above, 98 peer works) | JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) | Recommended | ₹14.96 L | 330 d | +52% | 63.0 | MEDIUM |
| Construction of Public Library cum Reading Room (Vachnalay) Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) | Recommended | ₹10.00 L | 365 d | +0% | 61.3 | MEDIUM |
| Khala construction work from Murba No. 186/31 to 186/36 Chak Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) | Recommended | ₹10.00 L | 346 d | 0% | 61.3 | MEDIUM |
| Construction of a Boundary Wall near Pabuji Temple, Village ₹1,000,000 against a ₹699,582 median for Religious & Cultural works in JAISALMER (43% above, 14 peer works) | JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) | Recommended | ₹10.00 L | 327 d | +43% | 61.1 | MEDIUM |
| Construction of Public Library at Near Veer Singh ki Daani, Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) | Recommended | ₹10.00 L | 240 d | +0% | 59.8 | MEDIUM |
| Construction of Public Library at near Ishan Khan-Ameen Khan 215 days beyond expected completion | JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) | Recommended | ₹10.00 L | 215 d | +0% | 59.4 | MEDIUM |
| Construction of Public Library at Near Lalsingh-Thagsingh ka 215 days beyond expected completion | JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) | Recommended | ₹10.00 L | 215 d | +0% | 59.4 | MEDIUM |
| Construction of Public Library with boundary wall at Near Ch 215 days beyond expected completion | JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) | Recommended | ₹10.00 L | 215 d | +0% | 59.4 | MEDIUM |
| Construction of Public Library at Near Bhagwansingh Kushalsi ₹1,500,000 against a ₹995,786 median for Education works in JAISALMER (51% above, 70 peer works) | JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) | Recommended | ₹15.00 L | 145 d | +51% | 57.2 | MEDIUM |
| For construction of a public reading room in the residence o 169 days beyond expected completion | JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) | Recommended | ₹10.00 L | 169 d | +2% | 56.9 | MEDIUM |
| Construction of Gravel Road from Village Dahua up to Village ₹2,964,000 against a ₹1,000,000 median for Roads & Paving works in JAISALMER (196% above, 67 peer works) | JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) | Recommended | ₹29.64 L | 45 d | +196% | 55.6 | MEDIUM |
| public bus stand construction work in Ramnagar village 175 days beyond expected completion | JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) | Recommended | ₹5.00 L | 175 d | -49% | 55.0 | MEDIUM |