Open this link on a larger screen to see the verification queue.
194 works across 1 implementing agency, recommended by 6 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | DUNGARPUR(DISTRICT COLLECTOR DUNGARPUR_IDA) 6 high risk | 194 | 73 | ₹12.18 Cr | 89 | 35.5 | MEHTA RAMESHKUMAR GOUTAMLAL 11% of spend · 72 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Chunnilal Garasiya Sitting Rajya Sabha | 99 | ₹6.70 Cr | 75 |
| Kanakmal Katara BANSWARA | 81 | ₹3.91 Cr | 8 |
| Madan Rathore Sitting Rajya Sabha | 6 | ₹42.00 L | 2 |
| Arjunlal Meena UDAIPUR | 4 | ₹39.97 L | 0 |
| Randeep Singh Surjewala Sitting Rajya Sabha | 2 | ₹35.00 L | 2 |
| Mukul Wasnik Sitting Rajya Sabha | 2 | ₹40.00 L | 2 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 80 | ₹4.97 Cr | 46 |
| Community Buildings | 34 | ₹2.26 Cr | 7 |
| Education | 33 | ₹1.89 Cr | 21 |
| Water | 24 | ₹1.50 Cr | 7 |
| Religious & Cultural | 10 | ₹66.95 L | 1 |
| Drainage & Sanitation | 5 | ₹25.50 L | 2 |
| Boundary & Protection | 4 | ₹37.50 L | 3 |
| Other | 1 | ₹3.00 L | 1 |
| Health | 1 | ₹13.00 L | 1 |
| Sports | 1 | ₹6.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| CC road
( CC road construction work from main road to Balbh ₹1,000,000 against a ₹500,000 median for Roads & Paving works in DUNGARPUR (100% above, 160 peer works) | DUNGARPUR(DISTRICT COLLECTOR DUNGARPUR_IDA) | Recommended | ₹10.00 L | 338 d | +100% | 75.1 | HIGH |
| Ground leveling work of Government Higher Secondary School D ₹1,000,000 against a ₹300,000 median for Education works in DUNGARPUR (233% above, 74 peer works) | DUNGARPUR(DISTRICT COLLECTOR DUNGARPUR_IDA) | Recommended | ₹10.00 L | 338 d | +233% | 75.1 | HIGH |
| CC Road Patidar Basti ₹1,000,000 against a ₹500,000 median for Roads & Paving works in DUNGARPUR (100% above, 160 peer works) | DUNGARPUR(DISTRICT COLLECTOR DUNGARPUR_IDA) | Recommended | ₹10.00 L | 338 d | +100% | 75.1 | HIGH |
| check dam construction work
(On Khokarwa pasture land) ₹1,000,000 against a ₹450,000 median for Water works in DUNGARPUR (122% above, 47 peer works) | DUNGARPUR(DISTRICT COLLECTOR DUNGARPUR_IDA) | Recommended | ₹10.00 L | 343 d | +122% | 75.1 | HIGH |
| CC road construction work
(CC road construction work in Kumh ₹1,000,000 against a ₹500,000 median for Roads & Paving works in DUNGARPUR (100% above, 160 peer works) | DUNGARPUR(DISTRICT COLLECTOR DUNGARPUR_IDA) | Recommended | ₹10.00 L | 343 d | +100% | 75.1 | HIGH |
| CC road construction work
(CC road construction work in enti ₹999,000 against a ₹500,000 median for Roads & Paving works in DUNGARPUR (100% above, 160 peer works) | DUNGARPUR(DISTRICT COLLECTOR DUNGARPUR_IDA) | Recommended | ₹9.99 L | 343 d | +100% | 75.0 | HIGH |
| CC Road from Main Road to Basti in Ranauli 235 days beyond expected completion | DUNGARPUR(DISTRICT COLLECTOR DUNGARPUR_IDA) | Recommended | ₹5.00 L | 235 d | 0% | 57.5 | MEDIUM |
| kisan prashin kendra ka nirman shree radha goshala vamsaa me ₹1,300,000 against a ₹699,950 median for Community Buildings works in DUNGARPUR (86% above, 73 peer works) | DUNGARPUR(DISTRICT COLLECTOR DUNGARPUR_IDA) | Recommended | ₹13.00 L | 596 d | +86% | 51.5 | MEDIUM |
| CC road work in tribal settlement village Bijawada Gram Panc 148 days beyond expected completion | DUNGARPUR(DISTRICT COLLECTOR DUNGARPUR_IDA) | Recommended | ₹4.50 L | 148 d | -10% | 51.5 | MEDIUM |
| Ring wall construction work on New Basti Anganwadi Bhawan Ro 148 days beyond expected completion | DUNGARPUR(DISTRICT COLLECTOR DUNGARPUR_IDA) | Recommended | ₹4.50 L | 148 d | -10% | 51.5 | MEDIUM |
| Culvert construction work in Nokna, Village Nokna, Gram Panc 148 days beyond expected completion | DUNGARPUR(DISTRICT COLLECTOR DUNGARPUR_IDA) | Recommended | ₹4.50 L | 148 d | -10% | 51.5 | MEDIUM |
| Ring wall construction work on Nogama drain, Gram Panchayat 148 days beyond expected completion | DUNGARPUR(DISTRICT COLLECTOR DUNGARPUR_IDA) | Recommended | ₹4.50 L | 148 d | 0% | 51.5 | MEDIUM |
| CC road work from Narendra Halu house to Rajmal Vaisaat hous 148 days beyond expected completion | DUNGARPUR(DISTRICT COLLECTOR DUNGARPUR_IDA) | Recommended | ₹4.50 L | 148 d | -10% | 51.5 | MEDIUM |
| Construction work of culvert in Khetor Fala, Village Bain, G 148 days beyond expected completion | DUNGARPUR(DISTRICT COLLECTOR DUNGARPUR_IDA) | Recommended | ₹4.50 L | 148 d | -10% | 51.5 | MEDIUM |
| Construction work of culvert with ring wall near the pond, V 148 days beyond expected completion | DUNGARPUR(DISTRICT COLLECTOR DUNGARPUR_IDA) | Recommended | ₹4.50 L | 148 d | -10% | 51.5 | MEDIUM |