69 works across 1 implementing agency, recommended by 7 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Didwana-Kuchaman(DISTRICT COLLECTOR Didwana Kuchaman_IDA) | 69 | 59 | ₹3.93 Cr | 13 | 19.6 | HA INFRA GLOBAL PRIVATE LIMITED 24% of spend · 116 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Hanuman Beniwal NAGAUR | 41 | ₹73.93 L | 0 |
| Sonia Gandhi Sitting Rajya Sabha | 9 | ₹83.60 L | 5 |
| Pramod Tiwari Sitting Rajya Sabha | 7 | ₹77.96 L | 3 |
| Mukul Wasnik Sitting Rajya Sabha | 6 | ₹94.96 L | 3 |
| Ghanshyam Tiwari Sitting Rajya Sabha | 3 | ₹25.00 L | 1 |
| Madan Rathore Sitting Rajya Sabha | 2 | ₹17.50 L | 0 |
| Randeep Singh Surjewala Sitting Rajya Sabha | 1 | ₹20.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 18 | ₹85.34 L | 3 |
| Education | 13 | ₹84.74 L | 1 |
| Roads & Paving | 9 | ₹54.95 L | 2 |
| Boundary & Protection | 8 | ₹12.86 L | 0 |
| Other | 5 | ₹27.50 L | 0 |
| Sports | 4 | ₹23.62 L | 1 |
| Drainage & Sanitation | 3 | ₹32.96 L | 0 |
| Street Lighting | 3 | ₹13.78 L | 3 |
| Water | 3 | ₹34.96 L | 2 |
| Religious & Cultural | 2 | ₹12.25 L | 1 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Public Library Bhawan with Digital Library i ₹2,500,000 against a ₹1,000,000 median for Education works in DIDWANA-KUCHAMAN (150% above, 40 peer works) | Didwana-Kuchaman(DISTRICT COLLECTOR Didwana Kuchaman_IDA) | Recommended | ₹25.00 L | 127 d | +150% | 63.5 | MEDIUM |
| Construction of Women Kaushal Vikas kendra at Gelasar Villag ₹2,000,000 against a ₹249,897 median for Community Buildings works in DIDWANA-KUCHAMAN (700% above, 23 peer works) | Didwana-Kuchaman(DISTRICT COLLECTOR Didwana Kuchaman_IDA) | Recommended | ₹20.00 L | 111 d | +700% | 61.3 | MEDIUM |
| To install rooftop solar panel plant in village Alakhpura (M Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Didwana-Kuchaman(DISTRICT COLLECTOR Didwana Kuchaman_IDA) | Recommended | ₹10.00 L | 438 d | +1% | 58.4 | MEDIUM |
| Construction of crematorium and resting place in Village Kya Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Didwana-Kuchaman(DISTRICT COLLECTOR Didwana Kuchaman_IDA) | Recommended | ₹10.00 L | 262 d | 0% | 56.5 | MEDIUM |
| For construction of community building in Gram Panchayat Bar Completed work has no photographic documentation on record | Didwana-Kuchaman(DISTRICT COLLECTOR Didwana Kuchaman_IDA) | Completed | ₹10.00 L | — | +300% | 50.4 | MEDIUM |
| Construction of a Rainwater Harvesting Tank at Village Pidwa Completed work has no photographic documentation on record | Didwana-Kuchaman(DISTRICT COLLECTOR Didwana Kuchaman_IDA) | Completed | ₹15.00 L | — | +202% | 50.4 | MEDIUM |
| Installation of High Mast Light at Near Common Bus Stand, Vi Completed work has no photographic documentation on record | Didwana-Kuchaman(DISTRICT COLLECTOR Didwana Kuchaman_IDA) | Completed | ₹4.98 L | — | +99% | 50.1 | MEDIUM |
| Construction of C.C. Block cum drain (Nali) from Damrikaran ₹2,000,000 against a ₹799,805 median for Roads & Paving works in DIDWANA-KUCHAMAN (150% above, 19 peer works) | Didwana-Kuchaman(DISTRICT COLLECTOR Didwana Kuchaman_IDA) | Recommended | ₹20.00 L | — | +150% | 45.9 | MEDIUM |
| Construction of Sakhi Bhawan in Gram Dikawa, Gram Panchayat ₹2,500,000 against a ₹249,897 median for Community Buildings works in DIDWANA-KUCHAMAN (900% above, 23 peer works) | Didwana-Kuchaman(DISTRICT COLLECTOR Didwana Kuchaman_IDA) | Recommended | ₹25.00 L | — | +900% | 45.9 | MEDIUM |
| Construction of a Tin Shed, Water Tank, and Garden at the Pu ₹1,499,709 against a ₹496,592 median for Water works in DIDWANA-KUCHAMAN (202% above, 9 peer works) | Didwana-Kuchaman(DISTRICT COLLECTOR Didwana Kuchaman_IDA) | Completed | ₹15.00 L | — | +202% | 45.9 | MEDIUM |
| Installation of High Mast Light at Village Barangana, Gram P Completed work has no photographic documentation on record | Didwana-Kuchaman(DISTRICT COLLECTOR Didwana Kuchaman_IDA) | Completed | ₹4.40 L | — | +76% | 44.4 | MEDIUM |
| Installation of High Mast Light at Village Dikawa, Gram Panc Completed work has no photographic documentation on record | Didwana-Kuchaman(DISTRICT COLLECTOR Didwana Kuchaman_IDA) | Completed | ₹4.40 L | — | +76% | 44.4 | MEDIUM |
| For the construction of C.C. block from the house of Asuram ₹1,499,044 against a ₹799,805 median for Roads & Paving works in DIDWANA-KUCHAMAN (87% above, 19 peer works) | Didwana-Kuchaman(DISTRICT COLLECTOR Didwana Kuchaman_IDA) | Completed | ₹14.99 L | — | +87% | 42.7 | MEDIUM |
| gram bajoli me samudayik nhawan nirman karya Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Didwana-Kuchaman(DISTRICT COLLECTOR Didwana Kuchaman_IDA) | Recommended | ₹2.50 L | 759 d | +0% | 37.7 | LOW |
| Work of tree plantation and installation of tree guards at p ₹1,000,000 against a ₹625,000 median for Other works in DIDWANA-KUCHAMAN (60% above, 10 peer works) | Didwana-Kuchaman(DISTRICT COLLECTOR Didwana Kuchaman_IDA) | Completed | ₹10.00 L | — | +60% | 35.9 | LOW |