192 works across 1 implementing agency, recommended by 10 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | ALWAR(DISTRICT COLLECTOR ALWAR_IDA) 1 high risk | 192 | 172 | ₹10.03 Cr | 21 | 14.0 | SHARMA CONTRACTOR 15% of spend · 480 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Balak Nath ALWAR | 75 | ₹3.81 Cr | 0 |
| Ranjeeta Koli BHARATPUR | 63 | ₹2.23 Cr | 0 |
| Rajyavardhan Singh Rathore JAIPUR RURAL | 21 | ₹1.50 Cr | 4 |
| Randeep Singh Surjewala Sitting Rajya Sabha | 7 | ₹66.51 L | 5 |
| Jaskaur Meena DAUSA | 7 | ₹37.82 L | 0 |
| Pramod Tiwari Sitting Rajya Sabha | 6 | ₹49.54 L | 4 |
| Mukul Wasnik Sitting Rajya Sabha | 6 | ₹54.55 L | 5 |
| Sonia Gandhi Sitting Rajya Sabha | 3 | ₹24.96 L | 1 |
| Ghanshyam Tiwari Sitting Rajya Sabha | 3 | ₹11.04 L | 2 |
| Madan Rathore Sitting Rajya Sabha | 1 | ₹5.25 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 115 | ₹6.51 Cr | 12 |
| Water | 26 | ₹52.73 L | 3 |
| Education | 14 | ₹95.24 L | 6 |
| Religious & Cultural | 11 | ₹47.36 L | 0 |
| Community Buildings | 11 | ₹77.47 L | 0 |
| Boundary & Protection | 6 | ₹24.45 L | 0 |
| Sports | 5 | ₹32.91 L | 0 |
| Other | 2 | ₹16.84 L | 0 |
| Street Lighting | 1 | ₹1.97 L | 0 |
| Health | 1 | ₹3.24 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Boundary Walls & Bathrooms with water tanks ₹999,212 against a ₹102,944 median for Water works in ALWAR (871% above, 50 peer works) | ALWAR(DISTRICT COLLECTOR ALWAR_IDA) | Recommended | ₹9.99 L | 432 d | +871% | 71.5 | HIGH |
| Construction of One Room at Rajkiya Uchch Madhyamik Vidyalay Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | ALWAR(DISTRICT COLLECTOR ALWAR_IDA) | Recommended | ₹9.00 L | 381 d | -8% | 58.2 | MEDIUM |
| 3-For construction of CC/interlocking tiles road from Indraj 337 days beyond expected completion | ALWAR(DISTRICT COLLECTOR ALWAR_IDA) | Recommended | ₹4.00 L | 337 d | -20% | 55.5 | MEDIUM |
| Construction of Public Library in Govt. Higher Secondary Sch 359 days beyond expected completion | ALWAR(DISTRICT COLLECTOR ALWAR_IDA) | Recommended | ₹5.00 L | 359 d | -49% | 55.2 | MEDIUM |
| Class room construction. Government Higher Secondary School, Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | ALWAR(DISTRICT COLLECTOR ALWAR_IDA) | Recommended | ₹7.00 L | 715 d | -29% | 51.0 | MEDIUM |
| For construction of security wall along CC road /interlockin Completed work has no photographic documentation on record | ALWAR(DISTRICT COLLECTOR ALWAR_IDA) | Completed | ₹9.98 L | — | +100% | 51.0 | MEDIUM |
| For construction of CC interlocking and tin sand in public c Completed work has no photographic documentation on record | ALWAR(DISTRICT COLLECTOR ALWAR_IDA) | Completed | ₹9.87 L | — | +98% | 50.4 | MEDIUM |
| Class room construction. Government Higher Secondary School, Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | ALWAR(DISTRICT COLLECTOR ALWAR_IDA) | Recommended | ₹5.15 L | 715 d | -48% | 48.6 | MEDIUM |
| Construction of a CC/Interlocking Tiles Road from near the r ₹1,500,000 against a ₹499,897 median for Roads & Paving works in ALWAR (200% above, 187 peer works) | ALWAR(DISTRICT COLLECTOR ALWAR_IDA) | Recommended | ₹15.00 L | — | +200% | 46.5 | MEDIUM |
| Water Tank with Jaali frame and construction of boundary wal ₹250,000 against a ₹102,944 median for Water works in ALWAR (143% above, 50 peer works) | ALWAR(DISTRICT COLLECTOR ALWAR_IDA) | Recommended | ₹2.50 L | — | +143% | 46.5 | MEDIUM |
| SINGAL PHASE BORING WITH ELECTRICITY CONNECTION WORK NEAR OM ₹554,381 against a ₹102,944 median for Water works in ALWAR (439% above, 50 peer works) | ALWAR(DISTRICT COLLECTOR ALWAR_IDA) | Completed | ₹5.54 L | — | +439% | 46.5 | MEDIUM |
| Construction of C.C. Road / Kharanja with Drain from the ho ₹1,494,708 against a ₹499,897 median for Roads & Paving works in ALWAR (199% above, 187 peer works) | ALWAR(DISTRICT COLLECTOR ALWAR_IDA) | Completed | ₹14.95 L | — | +199% | 46.5 | MEDIUM |
| Construction Work of CC/interlocking brics roads from Bhura ₹998,995 against a ₹499,897 median for Roads & Paving works in ALWAR (100% above, 187 peer works) | ALWAR(DISTRICT COLLECTOR ALWAR_IDA) | Completed | ₹9.99 L | — | +100% | 46.5 | MEDIUM |
| Construction of CC Interlocking Tiles Road from Bangan Ka Na ₹995,296 against a ₹499,897 median for Roads & Paving works in ALWAR (99% above, 187 peer works) | ALWAR(DISTRICT COLLECTOR ALWAR_IDA) | Completed | ₹9.95 L | — | +99% | 46.3 | MEDIUM |
| Construction Work of CC/Interlocking brics road from Roop Si ₹994,993 against a ₹499,897 median for Roads & Paving works in ALWAR (99% above, 187 peer works) | ALWAR(DISTRICT COLLECTOR ALWAR_IDA) | Completed | ₹9.95 L | — | +99% | 46.3 | MEDIUM |