93 works across 1 implementing agency, recommended by 6 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) 1 high risk | 93 | 58 | ₹6.00 Cr | 20 | 22.0 | EXECUTIVE ENGINEER CIVIL PB HEALTH CORP MOHALI 14% of spend · 155 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Manish Tewari ANANDPUR SAHIB | 78 | ₹2.36 Cr | 8 |
| Ashok Kumar Mittal Sitting Rajya Sabha | 7 | ₹1.10 Cr | 7 |
| Sant Balbir Singh Sitting Rajya Sabha | 4 | ₹37.32 L | 1 |
| Harbhajan Singh Sitting Rajya Sabha | 2 | ₹80.00 L | 2 |
| Raghav Chadha Sitting Rajya Sabha | 1 | ₹1.00 Cr | 1 |
| Vikramjit Singh Sahney Sitting Rajya Sabha | 1 | ₹37.57 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 28 | ₹1.21 Cr | 9 |
| Drainage & Sanitation | 12 | ₹57.23 L | 1 |
| Water | 12 | ₹26.51 L | 1 |
| Roads & Paving | 10 | ₹57.42 L | 1 |
| Religious & Cultural | 9 | ₹23.92 L | 2 |
| Sports | 8 | ₹1.67 Cr | 2 |
| Street Lighting | 5 | ₹12.80 L | 1 |
| Boundary & Protection | 3 | ₹43.07 L | 1 |
| Education | 3 | ₹11.00 L | 0 |
| Health | 2 | ₹75.00 L | 2 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Guru Hargobind Sahib Sports Park in Village- ₹5,000,000 against a ₹300,000 median for Sports works in RUPNAGAR (1567% above, 63 peer works) | RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) | Recommended | ₹50.00 L | 250 d | +1567% | 73.3 | HIGH |
| repair/renovation of main block (part-A) ground flour at PHC Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) | Recommended | ₹50.00 L | 604 d | 0% | 69.1 | MEDIUM |
| New Construction of Training Hall at PHC in Kiratpur Sahib D Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) | Recommended | ₹25.00 L | 607 d | 0% | 65.9 | MEDIUM |
| laying of interlock tiles in street at gajipur village lette ₹3,000,000 against a ₹300,000 median for Roads & Paving works in RUPNAGAR (900% above, 11 peer works) | RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) | Recommended | ₹30.00 L | 28 d | +900% | 52.2 | MEDIUM |
| Retaining Wall along with Pahari side and construction of pr ₹1,000,000 against a ₹500,000 median for Drainage & Sanitation works in RUPNAGAR (100% above, 17 peer works) | RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) | Recommended | ₹10.00 L | — | +100% | 48.4 | MEDIUM |
| construction of indoor stadium ₹10,000,000 against a ₹300,000 median for Sports works in RUPNAGAR (3233% above, 63 peer works) | RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) | Recommended | ₹1.00 Cr | — | +3233% | 48.4 | MEDIUM |
| For the Construction of Community Center ₹1,000,000 against a ₹374,734 median for Community Buildings works in RUPNAGAR (167% above, 60 peer works) | RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) | Recommended | ₹10.00 L | — | +167% | 48.4 | MEDIUM |
| For the Construction of Community Center ₹1,000,000 against a ₹374,734 median for Community Buildings works in RUPNAGAR (167% above, 60 peer works) | RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) | Recommended | ₹10.00 L | — | +167% | 48.4 | MEDIUM |
| For the construction Community Center ₹1,000,000 against a ₹374,734 median for Community Buildings works in RUPNAGAR (167% above, 60 peer works) | RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) | Recommended | ₹10.00 L | — | +167% | 48.4 | MEDIUM |
| For the construction of Community Center ₹1,000,000 against a ₹374,734 median for Community Buildings works in RUPNAGAR (167% above, 60 peer works) | RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) | Recommended | ₹10.00 L | — | +167% | 48.4 | MEDIUM |
| For the construction of Community Center ₹1,000,000 against a ₹374,734 median for Community Buildings works in RUPNAGAR (167% above, 60 peer works) | RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) | Recommended | ₹10.00 L | — | +167% | 48.4 | MEDIUM |
| For construction of SC Dharamshala in vill. Sakhpur 700 days beyond expected completion | RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) | Recommended | ₹2.50 L | 700 d | -33% | 47.3 | MEDIUM |
| For purchase of 3 Mobile Water Tankers by Municipal Council, ₹600,000 against a ₹350,000 median for Water works in RUPNAGAR (71% above, 40 peer works) | RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) | Recommended | ₹6.00 L | 574 d | +71% | 46.2 | MEDIUM |
| For construction of SC Dharamshala in vill. Seikhpur 616 days beyond expected completion | RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) | Recommended | ₹2.50 L | 616 d | -33% | 45.5 | MEDIUM |
| Construction of Flood control embankments to prevent flood i Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) | Completed | ₹37.57 L | — | 0% | 42.6 | MEDIUM |