177 works across 1 implementing agency, recommended by 6 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | GURDASPUR(DEPUTY COMMISSIONER GURDASPUR_IDA) | 177 | 159 | ₹10.44 Cr | 11 | 21.9 | Brightway Contractor and Developers 24% of spend · 41 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Sunny Deol GURDASPUR | 132 | ₹6.01 Cr | 8 |
| Som Parkash HOSHIARPUR | 39 | ₹59.91 L | 0 |
| Harbhajan Singh Sitting Rajya Sabha | 3 | ₹31.55 L | 1 |
| Raghav Chadha Sitting Rajya Sabha | 1 | ₹2.75 Cr | 1 |
| Sant Balbir Singh Sitting Rajya Sabha | 1 | ₹7.73 L | 0 |
| Vikramjit Singh Sahney Sitting Rajya Sabha | 1 | ₹68.84 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 104 | ₹2.28 Cr | 3 |
| Sports | 41 | ₹1.55 Cr | 1 |
| Education | 8 | ₹68.09 L | 0 |
| Equipment & Vehicles | 6 | ₹1.22 Cr | 3 |
| Religious & Cultural | 5 | ₹8.48 L | 0 |
| Roads & Paving | 5 | ₹60.75 L | 1 |
| Community Buildings | 3 | ₹98.25 L | 1 |
| Drainage & Sanitation | 2 | ₹24.05 L | 1 |
| Water | 1 | ₹2.00 L | 0 |
| Health | 1 | ₹2.32 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Installation of following 12 open gym instruments;
1. Surf 646 days beyond expected completion | GURDASPUR(DEPUTY COMMISSIONER GURDASPUR_IDA) | Recommended | ₹3.00 L | 646 d | +0% | 55.4 | MEDIUM |
| Construction of Computer Lab (Rs.9.21 Lakhs), Physics Lab ( ₹2,397,000 against a ₹772,663 median for Equipment & Vehicles works in GURDASPUR (210% above, 10 peer works) | GURDASPUR(DEPUTY COMMISSIONER GURDASPUR_IDA) | Recommended | ₹23.97 L | 549 d | +210% | 52.8 | MEDIUM |
| Establishment of Tourist/Entertainment Park including cultur ₹5,000,000 against a ₹167,365 median for Street Lighting works in GURDASPUR (2887% above, 149 peer works) | GURDASPUR(DEPUTY COMMISSIONER GURDASPUR_IDA) | Recommended | ₹50.00 L | 563 d | +2887% | 52.8 | MEDIUM |
| Construction of 5 seated toilet block consisting 2 each for ₹1,405,000 against a ₹365,000 median for Drainage & Sanitation works in GURDASPUR (285% above, 43 peer works) | GURDASPUR(DEPUTY COMMISSIONER GURDASPUR_IDA) | Recommended | ₹14.05 L | 636 d | +285% | 52.8 | MEDIUM |
| Construction of Community Hall at a convenient place in with ₹3,500,000 against a ₹500,000 median for Community Buildings works in GURDASPUR (600% above, 19 peer works) | GURDASPUR(DEPUTY COMMISSIONER GURDASPUR_IDA) | Recommended | ₹35.00 L | 647 d | +600% | 52.8 | MEDIUM |
| 120 Solar Lights ₹2,100,000 against a ₹167,365 median for Street Lighting works in GURDASPUR (1155% above, 149 peer works) | GURDASPUR(DEPUTY COMMISSIONER GURDASPUR_IDA) | Recommended | ₹21.00 L | 682 d | +1155% | 52.8 | MEDIUM |
| MPLAD Grant of rupees 78,78,000 for Procurement of 2 JCBs fo Completed work has no photographic documentation on record | GURDASPUR(DEPUTY COMMISSIONER GURDASPUR_IDA) | Completed | ₹68.84 L | — | +791% | 52.3 | MEDIUM |
| construction of Vishwakarma chowk at batala ₹2,000,000 against a ₹500,000 median for Roads & Paving works in GURDASPUR (300% above, 85 peer works) | GURDASPUR(DEPUTY COMMISSIONER GURDASPUR_IDA) | Recommended | ₹20.00 L | — | +300% | 47.8 | MEDIUM |
| strengthening of flood protection bandh embankment in gurdas Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | GURDASPUR(DEPUTY COMMISSIONER GURDASPUR_IDA) | Recommended | ₹2.75 Cr | 8 d | 0% | 45.7 | MEDIUM |
| Installation of 5 solar lights at main Chowk of the village 645 days beyond expected completion | GURDASPUR(DEPUTY COMMISSIONER GURDASPUR_IDA) | Recommended | ₹80,000 | 645 d | -52% | 42.6 | MEDIUM |
| Installation of a high power telescopic camera with display Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | GURDASPUR(DEPUTY COMMISSIONER GURDASPUR_IDA) | Recommended | ₹9.94 L | 589 d | +29% | 40.3 | MEDIUM |
| Installation of 15 solar lights from (i) Raju's Home to Gove ₹240,000 against a ₹167,365 median for Street Lighting works in GURDASPUR (43% above, 149 peer works) | GURDASPUR(DEPUTY COMMISSIONER GURDASPUR_IDA) | Recommended | ₹2.40 L | 646 d | +43% | 38.6 | LOW |
| Installation of 5 slolar lights at the main chowk of the vil 645 days beyond expected completion | GURDASPUR(DEPUTY COMMISSIONER GURDASPUR_IDA) | Recommended | ₹80,000 | 645 d | -52% | 36.8 | LOW |
| Installation of 5 solar lights from Primary School to main c 645 days beyond expected completion | GURDASPUR(DEPUTY COMMISSIONER GURDASPUR_IDA) | Recommended | ₹80,000 | 645 d | -52% | 36.8 | LOW |
| Installation of 10 solar Lights at CHowk adjacent to village 644 days beyond expected completion | GURDASPUR(DEPUTY COMMISSIONER GURDASPUR_IDA) | Recommended | ₹1.60 L | 644 d | -4% | 36.1 | LOW |