247 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Sundaragada(DISTRICT COLLECTOR SUNDARGARH_IDA) | 247 | 106 | ₹14.48 Cr | 59 | 26.2 | Geetanjali Traders 27% of spend · 83 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Jual Oram SUNDARGARH | 200 | ₹11.82 Cr | 33 |
| Sasmit Patra Sitting Rajya Sabha | 30 | ₹1.28 Cr | 17 |
| Dilip Kumar Ray Sitting Rajya Sabha | 17 | ₹1.38 Cr | 9 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 82 | ₹5.80 Cr | 29 |
| Education | 71 | ₹3.68 Cr | 2 |
| Roads & Paving | 34 | ₹1.69 Cr | 17 |
| Religious & Cultural | 22 | ₹1.43 Cr | 5 |
| Water | 10 | ₹56.92 L | 2 |
| Other | 8 | ₹19.78 L | 2 |
| Boundary & Protection | 5 | ₹26.50 L | 1 |
| Equipment & Vehicles | 4 | ₹19.20 L | 0 |
| Street Lighting | 4 | ₹24.98 L | 1 |
| Drainage & Sanitation | 4 | ₹24.70 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of CC Road from KalaPada to Raja Munda at Bhaba ₹600,000 against a ₹400,000 median for Roads & Paving works in SUNDARAGADA (50% above, 64 peer works) | Sundaragada(DISTRICT COLLECTOR SUNDARGARH_IDA) | Recommended | ₹6.00 L | 561 d | +50% | 62.3 | MEDIUM |
| Completion of Community Centre at Kinjirma Chruchpada 615 days beyond expected completion | Sundaragada(DISTRICT COLLECTOR SUNDARGARH_IDA) | Recommended | ₹4.00 L | 615 d | -20% | 57.7 | MEDIUM |
| Construction of C.C. road at Dhukupada 615 days beyond expected completion | Sundaragada(DISTRICT COLLECTOR SUNDARGARH_IDA) | Recommended | ₹4.00 L | 615 d | 0% | 57.7 | MEDIUM |
| Construction of guardwall from kadelpada to karkatpada road 615 days beyond expected completion | Sundaragada(DISTRICT COLLECTOR SUNDARGARH_IDA) | Recommended | ₹4.00 L | 615 d | 0% | 57.7 | MEDIUM |
| Construction of C. C. road from Basanti house to PWD road at 615 days beyond expected completion | Sundaragada(DISTRICT COLLECTOR SUNDARGARH_IDA) | Recommended | ₹4.00 L | 615 d | 0% | 57.7 | MEDIUM |
| Construction of C. C. road from main road to Badheipada at D 615 days beyond expected completion | Sundaragada(DISTRICT COLLECTOR SUNDARGARH_IDA) | Recommended | ₹4.00 L | 615 d | 0% | 57.7 | MEDIUM |
| Construction of C. C. road from Fagnu Rohidas home to Tilka 615 days beyond expected completion | Sundaragada(DISTRICT COLLECTOR SUNDARGARH_IDA) | Recommended | ₹3.00 L | 615 d | -25% | 56.7 | MEDIUM |
| Construction of CC Building near Radha Krushna Mandir, Jangl ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in SUNDARAGADA (100% above, 49 peer works) | Sundaragada(DISTRICT COLLECTOR SUNDARGARH_IDA) | Recommended | ₹10.00 L | 342 d | +100% | 54.8 | MEDIUM |
| Const. of rest room for visitors/patents at Jawahar Navodaya ₹1,000,000 against a ₹480,000 median for Education works in SUNDARAGADA (108% above, 122 peer works) | Sundaragada(DISTRICT COLLECTOR SUNDARGARH_IDA) | Recommended | ₹10.00 L | 342 d | +108% | 54.8 | MEDIUM |
| Const. of CC Building at Fakirmunda ₹1,000,000 against a ₹500,000 median for Community Buildings works in SUNDARAGADA (100% above, 149 peer works) | Sundaragada(DISTRICT COLLECTOR SUNDARGARH_IDA) | Recommended | ₹10.00 L | 342 d | +100% | 54.8 | MEDIUM |
| Construction of Community Centre infront of Oram Sanskrutika ₹1,000,000 against a ₹500,000 median for Community Buildings works in SUNDARAGADA (100% above, 149 peer works) | Sundaragada(DISTRICT COLLECTOR SUNDARGARH_IDA) | Recommended | ₹10.00 L | 343 d | +100% | 54.8 | MEDIUM |
| Construction of Crimination centre with Rest Shed at Birjabe ₹990,000 against a ₹500,000 median for Community Buildings works in SUNDARAGADA (98% above, 149 peer works) | Sundaragada(DISTRICT COLLECTOR SUNDARGARH_IDA) | Recommended | ₹9.90 L | 342 d | +98% | 54.3 | MEDIUM |
| Construction of CC Road from Kedia House to Indane Gas Godow Completed work has no photographic documentation on record | Sundaragada(DISTRICT COLLECTOR SUNDARGARH_IDA) | Completed | ₹10.00 L | — | +150% | 54.3 | MEDIUM |
| Construction of road from Court Road to Sapneswar Mandir Completed work has no photographic documentation on record | Sundaragada(DISTRICT COLLECTOR SUNDARGARH_IDA) | Completed | ₹10.00 L | — | +150% | 54.3 | MEDIUM |
| Const. of PDS distribution hall with waiting shed (2 Lakh) f ₹900,000 against a ₹500,000 median for Community Buildings works in SUNDARAGADA (80% above, 149 peer works) | Sundaragada(DISTRICT COLLECTOR SUNDARGARH_IDA) | Recommended | ₹9.00 L | 99 d | +80% | 54.1 | MEDIUM |