65 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | MALKANGIRI(District Collector Malkangiri_IDA) 1 high risk | 65 | 14 | ₹1.86 Cr | 51 | 36.0 | Prafulla Kumar Panda 38% of spend · 14 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Ramesh Chandra Majhi NABARANGPUR | 63 | ₹1.66 Cr | 49 |
| Manas Ranjan Mangaraj Sitting Rajya Sabha | 1 | ₹10.00 L | 1 |
| Sulata Deo Sitting Rajya Sabha | 1 | ₹10.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 52 | ₹1.41 Cr | 40 |
| Roads & Paving | 6 | ₹25.46 L | 5 |
| Education | 3 | ₹12.00 L | 3 |
| Boundary & Protection | 1 | ₹2.50 L | 1 |
| Religious & Cultural | 1 | ₹2.00 L | 1 |
| Drainage & Sanitation | 1 | ₹2.00 L | 1 |
| Street Lighting | 1 | ₹1.50 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| construction of the Lawyers Association Building District Ba ₹1,000,000 against a ₹300,000 median for Community Buildings works in MALKANGIRI (233% above, 101 peer works) | MALKANGIRI(District Collector Malkangiri_IDA) | Recommended | ₹10.00 L | 705 d | +233% | 78.0 | HIGH |
| Construction of Guard Wall and Culvert in Singarajkhunta vil Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | MALKANGIRI(District Collector Malkangiri_IDA) | Recommended | ₹10.00 L | 422 d | 0% | 65.3 | MEDIUM |
| community centre 579 days beyond expected completion | MALKANGIRI(District Collector Malkangiri_IDA) | Recommended | ₹2.00 L | 579 d | -33% | 60.2 | MEDIUM |
| community centre 579 days beyond expected completion | MALKANGIRI(District Collector Malkangiri_IDA) | Recommended | ₹2.00 L | 579 d | -33% | 60.2 | MEDIUM |
| Gopi pujari community centre ₹500,000 against a ₹300,000 median for Community Buildings works in MALKANGIRI (67% above, 101 peer works) | MALKANGIRI(District Collector Malkangiri_IDA) | Recommended | ₹5.00 L | 579 d | +67% | 49.6 | MEDIUM |
| Banik Samaj community centre ₹500,000 against a ₹300,000 median for Community Buildings works in MALKANGIRI (67% above, 101 peer works) | MALKANGIRI(District Collector Malkangiri_IDA) | Recommended | ₹5.00 L | 579 d | +67% | 49.6 | MEDIUM |
| Basanti Community centre mv-72 ₹500,000 against a ₹300,000 median for Community Buildings works in MALKANGIRI (67% above, 101 peer works) | MALKANGIRI(District Collector Malkangiri_IDA) | Recommended | ₹5.00 L | 579 d | +67% | 49.6 | MEDIUM |
| Boundary wall of Siva Community Center at Dike-3 GP- Nakamam 576 days beyond expected completion | MALKANGIRI(District Collector Malkangiri_IDA) | Recommended | ₹4.00 L | 576 d | +33% | 41.3 | MEDIUM |
| Gramadevi Community Centre 579 days beyond expected completion | MALKANGIRI(District Collector Malkangiri_IDA) | Recommended | ₹4.00 L | 579 d | +33% | 41.3 | MEDIUM |
| Development of Malkangiri College , Malkangiri 553 days beyond expected completion | MALKANGIRI(District Collector Malkangiri_IDA) | Recommended | ₹5.00 L | 553 d | 0% | 41.2 | MEDIUM |
| Addl class room At MPV-82 579 days beyond expected completion | MALKANGIRI(District Collector Malkangiri_IDA) | Recommended | ₹5.00 L | 579 d | 0% | 41.0 | MEDIUM |
| CC road At MV-79 Tandbai 579 days beyond expected completion | MALKANGIRI(District Collector Malkangiri_IDA) | Recommended | ₹5.00 L | 579 d | 0% | 41.0 | MEDIUM |
| Radhakrishna community center at MV -90 GP-Kalimela 553 days beyond expected completion | MALKANGIRI(District Collector Malkangiri_IDA) | Recommended | ₹2.00 L | 553 d | -33% | 40.5 | MEDIUM |
| CC road at Singrajkonda Gp- Manyamkonda 553 days beyond expected completion | MALKANGIRI(District Collector Malkangiri_IDA) | Recommended | ₹2.00 L | 553 d | 0% | 40.5 | MEDIUM |
| Guard wall at Gangla to Ashram school Gp- Gangla 553 days beyond expected completion | MALKANGIRI(District Collector Malkangiri_IDA) | Recommended | ₹2.00 L | 553 d | -60% | 40.5 | MEDIUM |