Open this link on a larger screen to see the verification queue.
108 works across 1 implementing agency, recommended by 1 member of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | JHARSUGUDA(DISTRICT COLLECTORJHARSUGUDA_IDA) | 108 | 76 | ₹3.10 Cr | 4 | 17.6 | MANINI MEHER 15% of spend · 36 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Suresh Kumar Pujari BARGARH | 108 | ₹3.10 Cr | 4 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 55 | ₹1.54 Cr | 3 |
| Religious & Cultural | 32 | ₹87.43 L | 1 |
| Education | 15 | ₹46.34 L | 0 |
| Roads & Paving | 3 | ₹10.50 L | 0 |
| Boundary & Protection | 2 | ₹7.99 L | 0 |
| Drainage & Sanitation | 1 | ₹3.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of CC Building Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JHARSUGUDA(DISTRICT COLLECTORJHARSUGUDA_IDA) | Recommended | ₹3.00 L | 735 d | 0% | 58.6 | MEDIUM |
| Completion of Open Mandap 626 days beyond expected completion | JHARSUGUDA(DISTRICT COLLECTORJHARSUGUDA_IDA) | Recommended | ₹2.00 L | 626 d | -33% | 55.9 | MEDIUM |
| Construction of Community Center at back side of Tarini Mand ₹500,000 against a ₹300,000 median for Community Buildings works in JHARSUGUDA (67% above, 75 peer works) | JHARSUGUDA(DISTRICT COLLECTORJHARSUGUDA_IDA) | Recommended | ₹5.00 L | 650 d | +67% | 44.9 | MEDIUM |
| Completion of newly constructed Community Hall ₹500,000 against a ₹300,000 median for Community Buildings works in JHARSUGUDA (67% above, 75 peer works) | JHARSUGUDA(DISTRICT COLLECTORJHARSUGUDA_IDA) | Recommended | ₹5.00 L | 680 d | +67% | 44.9 | MEDIUM |
| Completion of CC near Shiva Temple Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JHARSUGUDA(DISTRICT COLLECTORJHARSUGUDA_IDA) | Recommended | ₹1.50 L | 734 d | -50% | 39.4 | LOW |
| Completion of Community Center near Hanuman Mandap Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JHARSUGUDA(DISTRICT COLLECTORJHARSUGUDA_IDA) | Recommended | ₹1.50 L | 734 d | -50% | 39.4 | LOW |
| Additional Construction of CC at Guthanipada Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JHARSUGUDA(DISTRICT COLLECTORJHARSUGUDA_IDA) | Recommended | ₹2.50 L | 735 d | 0% | 38.7 | LOW |
| Construction of CC Building near Aurobindo Institute of Inte Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JHARSUGUDA(DISTRICT COLLECTORJHARSUGUDA_IDA) | Recommended | ₹3.00 L | 734 d | 0% | 38.7 | LOW |
| Construction of Dining Hall at KMB High School Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JHARSUGUDA(DISTRICT COLLECTORJHARSUGUDA_IDA) | Recommended | ₹3.00 L | 735 d | 0% | 38.6 | LOW |
| Further Construction of CC Building near Sabri Narayan Templ Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JHARSUGUDA(DISTRICT COLLECTORJHARSUGUDA_IDA) | Recommended | ₹3.00 L | 735 d | 0% | 38.6 | LOW |
| Construction of CC Building at Barhamunda Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JHARSUGUDA(DISTRICT COLLECTORJHARSUGUDA_IDA) | Recommended | ₹3.00 L | 735 d | 0% | 38.6 | LOW |
| Construction of Kalyan Mandap at Mundapada Chowk Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JHARSUGUDA(DISTRICT COLLECTORJHARSUGUDA_IDA) | Recommended | ₹3.00 L | 735 d | 0% | 38.6 | LOW |
| Construction of Kitchen Shed near Shiba Temple 716 days beyond expected completion | JHARSUGUDA(DISTRICT COLLECTORJHARSUGUDA_IDA) | Recommended | ₹2.00 L | 716 d | -33% | 37.8 | LOW |
| Construction of Community Center at Gayatri Nagar 715 days beyond expected completion | JHARSUGUDA(DISTRICT COLLECTORJHARSUGUDA_IDA) | Recommended | ₹3.00 L | 715 d | 0% | 37.7 | LOW |
| Construction of Kalyan Mandap at Harijanpada (Ragiatikra) 716 days beyond expected completion | JHARSUGUDA(DISTRICT COLLECTORJHARSUGUDA_IDA) | Recommended | ₹3.00 L | 716 d | 0% | 37.7 | LOW |