137 works across 1 implementing agency, recommended by 5 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | BHADRAK(DISTRICT COLLECTOR BHADRAK_IDA) | 137 | 19 | ₹7.88 Cr | 6 | 20.5 | NRUSINGHA CHARAN DUTTA 4% of spend · 37 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Avimanyu Sethi BHADRAK | 130 | ₹6.53 Cr | 4 |
| Manas Ranjan Mangaraj Sitting Rajya Sabha | 4 | ₹9.50 L | 0 |
| Sulata Deo Sitting Rajya Sabha | 1 | ₹5.00 L | 0 |
| Sasmit Patra Sitting Rajya Sabha | 1 | ₹20.00 L | 1 |
| Ashwini Vaishnaw Sitting Rajya Sabha | 1 | ₹1.00 Cr | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 59 | ₹3.16 Cr | 3 |
| Education | 26 | ₹2.11 Cr | 1 |
| Roads & Paving | 24 | ₹1.05 Cr | 2 |
| Religious & Cultural | 12 | ₹55.00 L | 0 |
| Street Lighting | 4 | ₹20.00 L | 0 |
| Other | 3 | ₹20.00 L | 0 |
| Boundary & Protection | 3 | ₹13.00 L | 0 |
| Health | 2 | ₹28.00 L | 0 |
| Sports | 2 | ₹12.00 L | 0 |
| Drainage & Sanitation | 2 | ₹8.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Community Centre at Bhadrakali Sahi near Bha ₹1,000,000 against a ₹400,000 median for Community Buildings works in BHADRAK (150% above, 101 peer works) | BHADRAK(DISTRICT COLLECTOR BHADRAK_IDA) | Recommended | ₹10.00 L | 180 d | +150% | 55.1 | MEDIUM |
| Construction of Madina Maidan Community Hall At Madina Maida ₹2,000,000 against a ₹400,000 median for Community Buildings works in BHADRAK (400% above, 101 peer works) | BHADRAK(DISTRICT COLLECTOR BHADRAK_IDA) | Recommended | ₹20.00 L | — | +400% | 50.1 | MEDIUM |
| Construction of new building of Dolasahi Government U.P.M.E. ₹10,000,000 against a ₹500,000 median for Education works in BHADRAK (1900% above, 45 peer works) | BHADRAK(DISTRICT COLLECTOR BHADRAK_IDA) | Recommended | ₹1.00 Cr | — | +1900% | 50.1 | MEDIUM |
| Const. of C.C. road with culvert village Deulipadi, Rahanian ₹600,000 against a ₹300,000 median for Roads & Paving works in BHADRAK (100% above, 71 peer works) | BHADRAK(DISTRICT COLLECTOR BHADRAK_IDA) | Recommended | ₹6.00 L | 99 d | +100% | 43.8 | MEDIUM |
| Construction of Community Centre at Manjuri road Bazar near ₹600,000 against a ₹300,000 median for Roads & Paving works in BHADRAK (100% above, 71 peer works) | BHADRAK(DISTRICT COLLECTOR BHADRAK_IDA) | Recommended | ₹6.00 L | 99 d | +100% | 43.8 | MEDIUM |
| Construction of Community Centre at Dhamara village near Dha ₹1,000,000 against a ₹400,000 median for Community Buildings works in BHADRAK (150% above, 101 peer works) | BHADRAK(DISTRICT COLLECTOR BHADRAK_IDA) | Recommended | ₹10.00 L | 99 d | +150% | 43.8 | MEDIUM |
| Electrification of Village Erendei,Kadabarang GP. ₹500,000 against a ₹274,725 median for Street Lighting works in BHADRAK (82% above, 12 peer works) | BHADRAK(DISTRICT COLLECTOR BHADRAK_IDA) | Recommended | ₹5.00 L | 99 d | +82% | 39.3 | LOW |
| Construction of Community Centre at Pujari Sahi. 180 days beyond expected completion | BHADRAK(DISTRICT COLLECTOR BHADRAK_IDA) | Recommended | ₹4.00 L | 180 d | 0% | 36.7 | LOW |
| Construction of drainage system from Anirodha Sethy house to 180 days beyond expected completion | BHADRAK(DISTRICT COLLECTOR BHADRAK_IDA) | Recommended | ₹5.00 L | 180 d | 0% | 36.6 | LOW |
| Construction of Building at Utukuda M.E. School 180 days beyond expected completion | BHADRAK(DISTRICT COLLECTOR BHADRAK_IDA) | Recommended | ₹5.00 L | 180 d | 0% | 36.6 | LOW |
| Construction of Bathing Ghat at Basudevpur near Gamei River 180 days beyond expected completion | BHADRAK(DISTRICT COLLECTOR BHADRAK_IDA) | Recommended | ₹5.00 L | 180 d | 0% | 36.6 | LOW |
| Construction of building Aruha Grama Panchayat High School. 180 days beyond expected completion | BHADRAK(DISTRICT COLLECTOR BHADRAK_IDA) | Recommended | ₹5.00 L | 180 d | 0% | 36.6 | LOW |
| Construction of Building Saraswati Sisu Bidya Mandir, Basude 180 days beyond expected completion | BHADRAK(DISTRICT COLLECTOR BHADRAK_IDA) | Recommended | ₹5.00 L | 180 d | 0% | 36.6 | LOW |
| Construction of Boundary wall of Govt. Primary School, Natag 180 days beyond expected completion | BHADRAK(DISTRICT COLLECTOR BHADRAK_IDA) | Recommended | ₹3.00 L | 180 d | -40% | 36.4 | LOW |
| Const. of C.C. road with culvert from Malada Shyamsudarpur t ₹500,000 against a ₹300,000 median for Roads & Paving works in BHADRAK (67% above, 71 peer works) | BHADRAK(DISTRICT COLLECTOR BHADRAK_IDA) | Recommended | ₹5.00 L | 99 d | +67% | 35.5 | LOW |