Open this link on a larger screen to see the verification queue.
49 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Anugola(DISTRICT COLLECTORANGUL_IDA) | 49 | 11 | ₹1.75 Cr | 13 | 35.4 | Fani Bhusan Biswal 10% of spend · 12 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Mahesh Sahoo DHENKANAL | 48 | ₹1.65 Cr | 12 |
| Sulata Deo Sitting Rajya Sabha | 1 | ₹10.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 16 | ₹74.49 L | 2 |
| Roads & Paving | 16 | ₹48.00 L | 10 |
| Education | 10 | ₹36.00 L | 0 |
| Street Lighting | 6 | ₹14.40 L | 0 |
| Drainage & Sanitation | 1 | ₹2.00 L | 1 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction for Building for Radio Sarvodaya Bajirout Chhat 224 days beyond expected completion | Anugola(DISTRICT COLLECTORANGUL_IDA) | Recommended | ₹10.00 L | 224 d | +25% | 61.3 | MEDIUM |
| Construction of CC Road Bira Sethy house to Mendabereni Temp 692 days beyond expected completion | Anugola(DISTRICT COLLECTORANGUL_IDA) | Recommended | ₹2.00 L | 692 d | -20% | 58.6 | MEDIUM |
| Construction of CC Road Bira Sethy house to Mendabereni Temp 692 days beyond expected completion | Anugola(DISTRICT COLLECTORANGUL_IDA) | Recommended | ₹2.00 L | 692 d | -20% | 58.6 | MEDIUM |
| Construction of CC Road from Kuram Bahal to Karadakhaman, Su ₹500,000 against a ₹250,000 median for Roads & Paving works in ANUGOLA (100% above, 16 peer works) | Anugola(DISTRICT COLLECTORANGUL_IDA) | Recommended | ₹5.00 L | 635 d | +100% | 56.3 | MEDIUM |
| Construction of CC Road from Suleipal Hadisahi to Paramapasi ₹500,000 against a ₹250,000 median for Roads & Paving works in ANUGOLA (100% above, 16 peer works) | Anugola(DISTRICT COLLECTORANGUL_IDA) | Recommended | ₹5.00 L | 635 d | +100% | 56.3 | MEDIUM |
| Construction of Old Age Home at Durgaprasadpur, GP- Talamul Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Anugola(DISTRICT COLLECTORANGUL_IDA) | Recommended | ₹10.00 L | 645 d | +25% | 44.5 | MEDIUM |
| Construction of CC road Akhil Panda house to PWD road news R 692 days beyond expected completion | Anugola(DISTRICT COLLECTORANGUL_IDA) | Recommended | ₹2.00 L | 692 d | -20% | 40.2 | MEDIUM |
| Construction of CC road Bantala PWD Road Cheptigadia Pond of 692 days beyond expected completion | Anugola(DISTRICT COLLECTORANGUL_IDA) | Recommended | ₹2.00 L | 692 d | -20% | 40.2 | MEDIUM |
| Construction of CC Road Alla Sahu house to Mahammad Siraj Ho 692 days beyond expected completion | Anugola(DISTRICT COLLECTORANGUL_IDA) | Recommended | ₹2.00 L | 692 d | -20% | 40.2 | MEDIUM |
| Constructin of CC Drain Sani Mandira to Adikanda Naik House 692 days beyond expected completion | Anugola(DISTRICT COLLECTORANGUL_IDA) | Recommended | ₹2.00 L | 692 d | 0% | 40.2 | MEDIUM |
| Construction of CC road Lingaranadi to Airtel Tower at Purik 692 days beyond expected completion | Anugola(DISTRICT COLLECTORANGUL_IDA) | Recommended | ₹2.00 L | 692 d | -20% | 40.2 | MEDIUM |
| Construction of CC Road Similichhuin RD Road to Maa Kousalya 692 days beyond expected completion | Anugola(DISTRICT COLLECTORANGUL_IDA) | Recommended | ₹2.00 L | 692 d | -20% | 40.2 | MEDIUM |
| Construction of CC Road Nabasahu house to Dibakara Sahu Plot 692 days beyond expected completion | Anugola(DISTRICT COLLECTORANGUL_IDA) | Recommended | ₹2.00 L | 692 d | -20% | 40.2 | MEDIUM |
| Construction of Community Cultural Activities Hall at Chand 645 days beyond expected completion | Anugola(DISTRICT COLLECTORANGUL_IDA) | Recommended | ₹4.00 L | 645 d | -50% | 39.8 | LOW |
| Construction of Community Centre at Bentapur, Vill- Bentapur 645 days beyond expected completion | Anugola(DISTRICT COLLECTORANGUL_IDA) | Recommended | ₹4.00 L | 645 d | -50% | 39.8 | LOW |