43 works across 1 implementing agency, recommended by 1 member of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | MAMIT(DEPUTY COMMISSIONER MAMIT) | 43 | 34 | ₹2.06 Cr | 0 | 10.0 | VC PHULDUNGSEI ZAMPUI 15% of spend · 18 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Richard Vanlalhmangaiha MIZORAM | 43 | ₹2.06 Cr | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 19 | ₹1.13 Cr | 0 |
| Community Buildings | 10 | ₹44.50 L | 0 |
| Education | 9 | ₹27.50 L | 0 |
| Water | 2 | ₹5.00 L | 0 |
| Boundary & Protection | 1 | ₹3.00 L | 0 |
| Drainage & Sanitation | 1 | ₹2.50 L | 0 |
| Sports | 1 | ₹9.90 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| construction of link road to Tlangkhang zau 164 days beyond expected completion | MAMIT(DEPUTY COMMISSIONER MAMIT) | Recommended | ₹9.50 L | 164 d | 0% | 32.1 | LOW |
| Upgradation/Renovationof Thaidawr to Zomuantlang road, Phuld Completed work has no photographic documentation on record | MAMIT(DEPUTY COMMISSIONER MAMIT) | Completed | ₹9.90 L | — | +4% | 30.1 | LOW |
| Construction of MHIP House at Lengpui Completed work has no photographic documentation on record | MAMIT(DEPUTY COMMISSIONER MAMIT) | Completed | ₹7.00 L | — | +180% | 29.8 | LOW |
| Renovation of Mamit High School - II Completed work has no photographic documentation on record | MAMIT(DEPUTY COMMISSIONER MAMIT) | Completed | ₹5.00 L | — | +100% | 29.8 | LOW |
| Constructon of PCC flooring from BRTF Hall to Community hal Completed work has no photographic documentation on record | MAMIT(DEPUTY COMMISSIONER MAMIT) | Completed | ₹10.00 L | — | +300% | 29.8 | LOW |
| Construction of rest house (Vertical extension) of BNRGSK bu Completed work has no photographic documentation on record | MAMIT(DEPUTY COMMISSIONER MAMIT) | Completed | ₹10.00 L | — | +300% | 29.8 | LOW |
| Upgradation/Renovationof Thaidawr to Zomuantlang road, Phuld Completed work has no photographic documentation on record | MAMIT(DEPUTY COMMISSIONER MAMIT) | Completed | ₹10.00 L | — | +5% | 29.7 | LOW |
| Construction of High School Teacher's quarters at Dampui ₹500,000 against a ₹250,000 median for Education works in MAMIT (100% above, 10 peer works) | MAMIT(DEPUTY COMMISSIONER MAMIT) | Recommended | ₹5.00 L | — | +100% | 25.3 | LOW |
| Construction of Public Playground Completed work has no photographic documentation on record | MAMIT(DEPUTY COMMISSIONER MAMIT) | Completed | ₹9.90 L | — | 0% | 10.1 | LOW |
| Construction of Link road at Tlangkhang Completed work has no photographic documentation on record | MAMIT(DEPUTY COMMISSIONER MAMIT) | Completed | ₹10.00 L | — | +5% | 9.7 | LOW |
| Construction of PCC flooring at Vaisamtlang , Lengpui venghl Completed work has no photographic documentation on record | MAMIT(DEPUTY COMMISSIONER MAMIT) | Completed | ₹10.00 L | — | +5% | 9.7 | LOW |
| Hmun village extention road at Hmunpui Completed work has no photographic documentation on record | MAMIT(DEPUTY COMMISSIONER MAMIT) | Completed | ₹10.00 L | — | +5% | 9.7 | LOW |
| Construction of link road (chalkawn to Charkawn) Completed work has no photographic documentation on record | MAMIT(DEPUTY COMMISSIONER MAMIT) | Completed | ₹10.00 L | — | +5% | 9.7 | LOW |
| Construction of LMV bridge over Sunhlu lui at WRC approach r Completed work has no photographic documentation on record | MAMIT(DEPUTY COMMISSIONER MAMIT) | Completed | ₹10.00 L | — | +5% | 9.7 | LOW |
| Construction of Foothpath Pukzing Main Road Near Pu Samuela Completed work has no photographic documentation on record | MAMIT(DEPUTY COMMISSIONER MAMIT) | Completed | ₹1.50 L | — | -84% | 6.9 | LOW |